00:20:37 welcome back everyone we're now going to resume hearing evidence from mr david jones i'll begin by checking that mr jones can see me and hear me well mr jones good
00:20:49 see me and hear me well mr jones good afternoon yes yes i can good thank you very much and uh
00:20:53 uh are you ready to continue is there anything you want to raise first uh no no i'm ready to carry out very good in that case i'll invite this troop to go on with her questions yes it's true thank you mr jones i want
00:21:05 yes it's true thank you mr jones i want to take us forward a little in the timeline so i'm going to ask you to look now at an email which is at labc302281
00:21:18 it's a series of emails rather from january 2009
00:21:28 if we go to the second email in the chain please which is yours you sent an email to phil harrison at the labc on the 14th of january 2009 at 1107. do you see it
00:21:41 2009 at 1107. do you see it yes i do i i just want to read through that with you you say dear phil i've been following up on your email below with regards to type approval for kingspan's brainscreen
00:21:52 type approval for kingspan's brainscreen cladding insulation board if i understand the process correctly i now need to pass it back to labc for an invoice to be raised etc i met with andrew pack before christmas
00:22:03 i met with andrew pack before christmas to discuss what we could offer them through the type approval scheme and suggested that in view of the scope of the certificate the minimum fee of 500 pounds would be adequate
00:22:13 adequate he was keen to proceed with this after our meeting and so i have since carried on
00:22:18 on and done the necessary work to produce the certificate though i haven't forwarded anything on to andrew as yet just pausing there on what basis
00:22:29 just pausing there on what basis had you determined at that stage that the minimum fee for your work of 500 pounds would be adequate
00:22:37 adequate i believe that was that was based on the original
00:22:41 original brief given to me by abc the subsequent discussion with um with kingspan about what they wanted uh and sort of a final agreement that yes that that scope is
00:22:53 yes that that scope is is if everybody had a common understanding then that that was the scope
00:22:57 scope and that that was the fee that would be that would be done and i believe going back further i'm sure there were conversations with um labc where the minimum fee was was discussed
00:23:07 discussed you know on the basis that actually you're not going any further than the bba certificate so it's not going to be a
00:23:13 a long drawn out process yeah so it was fairly straightforward so in your mind the minimum fee was appropriate is that
00:23:22 that is that it for what had been asked for of us
00:23:25 of us yes yes if we go on in that email you say this is at the third paragraph the most we can really offer in this case would be a product approval
00:23:37 case would be a product approval k15 is just the insulation component of the rain screen walling system both the inner structural frame and the rain screen cladding itself are unknown variables
00:23:46 variables produced by a third party and so system approval would be impossible to pin down i did emphasize this to andrew to be clear that the type approval would not go any further
00:23:57 go any further than the current bba certificate but he was happy that it would still be worthwhile if only to get the labc seal of approval and so again just pausing there i think
00:24:09 and so again just pausing there i think that accords would you say with what you have told us about kingspan's aim in having their products associated with the labc brand it was it was a marketing
00:24:21 the labc brand it was it was a marketing aim
00:24:23 aim yes i i think that it it does sort of um support that and also shows that i'm still wrangling over this um this difference between product and system at this stage
00:24:35 system at this stage it does doesn't it because in that paragraph if we look at the third line you've actually said a system approval would be impossible to pin down
00:24:44 pin down yes so can i take it from that given that by the time the certificate was issued it was in fact a system of approval
00:24:52 approval that you had done further work and you had developed your thinking further and found a way forward to make it into a system approval uh no because the report that i'm
00:25:05 uh no because the report that i'm forwarding to phil harrison undercover of this email is the same report that went to them finally um to for consideration against the certificate so
00:25:16 against the certificate so the report as we or my report as we've seen it
00:25:19 seen it was already in existence at this stage but i think throughout it was it was always in my mind a product approval and even though ultimately it came out from labc
00:25:29 from labc on a form titled system approval to to me it was still essentially a product approval uh in that how could it be anything else because only one product is actually defined in it
00:25:39 it and i think that the fact that the certificate was titled system approval comes back to this um original point of labc that the terminology is all wrong we have to call it system approval
00:25:50 we have to call it system approval because that's what our forms say yes would you agree despite the fact that to you it was always a product approval that that would not be apparent to a reader of the certificate
00:26:01 apparent to a reader of the certificate reading it now i can see that yes yes where labc perhaps said don't worry about it we're going to be revamping this soon but just go with what you've got actually we shouldn't have done that it should
00:26:12 we shouldn't have done that it should have been it should have been made clear that we were just talking about a product when did you come to determine that mr jones that it should have been made clear and it shouldn't have been done in this way i think that's
00:26:24 i think that's more over over the last um year and a half in in seeing perhaps how this certificate was used after it sort of left labc and and what kingsmen
00:26:35 sort of left labc and and what kingsmen were doing with it yes all right if we can go on in this email if we could scroll down or if we start at the final paragraph we can see there
00:26:46 can see there you go on to give mr harrison um an outline of how you how you intend to approach your summary and you say this i would suggest then that the type approval certificate be for k15
00:26:58 approval certificate be for k15 as part of a generic but undefined system and refer to the following documents all attached our summary of building regs compliance issues considered and then if we can go on down please bba
00:27:11 and then if we can go on down please bba certificate 084582 kingspan's own literature i would be grateful if you could let me know what the next step should be yes yes and attached to this was your type
00:27:23 and attached to this was your type approval summary was it yes right if we can go up then please to mr harrison's response to you which is at the top of page one
00:27:34 at the top of page one he says there and this is the 19th of january
00:27:38 january good morning dave attached for your use as agreed
00:27:42 as agreed are the latest versions of a type approval application form and the compliance declaration thank you for sorting this out so thoroughly did you take from
00:27:53 so thoroughly did you take from this email approval by the labc of the work you had done
00:28:00 i did at that stage yes although um knowing that i was sending them the type of approval at this stage for for the first time uh i obviously knew that the checking process hadn't yet occurred so
00:28:12 process hadn't yet occurred so so i knew that was still to come i see and and i imagine that during the course of that process if any queries arose then then labc would come back to me to discuss yes do you know whether phil
00:28:25 to discuss yes do you know whether phil harrison
00:28:26 harrison had a technical role at the labc uh i didn't know anything much about phil harrison's background um his his title i think was business
00:28:38 um his his title i think was business development which suggests marketing he does uh but i don't know whether you know he could have been a technical practitioner who went into marketing sure all right i'm sorry i overspoke you
00:28:49 sure all right i'm sorry i overspoke you again
00:28:51 again that's okay great uh he mentioned in that email a compliance declaration form he sent that to you if we can go to that now please that's at hbc6021
00:29:15 and to the second page please
00:29:18 that is the compliance declaration form isn't it
00:29:22 isn't it uh yes did you fill out the main body of that form
00:29:30 i believe i did yes yes so you would have i think you've blacked out no or yes um as appropriate in the middle section
00:29:41 um as appropriate in the middle section extent of recommended regulatory approval
00:29:44 approval is that right yes and if we go to the bottom
00:29:48 bottom of that page please we can see that the document is unsigned and undated
00:29:57 undated did you understand that to be for signature and dating by the labc was it for them to declare compliance or you
00:30:06 you uh my my understanding was that it was for them to declare compliance because this this um what i was sending them at this stage still had a number of processes to go
00:30:18 still had a number of processes to go through before it became an abc certificate so ultimately compliance would be the sum of all these exercises including the checking that was still to come
00:30:29 the checking that was still to come um so no i wouldn't have i wouldn't have anticipated when i sent this that this was the be all and end or this is how it would look this was just me sending to labc everything that i'd considered
00:30:40 considered for them to to take take on board and for them to check as necessary and for them to
00:30:46 them to ultimately issue a certificate i think the fact that it's not signed is more likely to be because i sent it as an electronic document and didn't sign it fine all right i want to take you now please
00:30:57 to take you now please to the labc approval certificate and to the summary that you prepared so if we can go please to kin405705 please
00:31:16 so that's the certificate itself at page one and it's stated in the right top hand corner the first of may 2009 yes yes and just looking through it
00:31:27 yes yes and just looking through it uh at section one we see the certificate holders details that's obviously kingspan
00:31:34 kingspan and then we see at section two system title
00:31:37 title description kingspan call them k15 rain screen board i mean we've been over this but k-15 is not a system is it no no it's not
00:31:50 at section three if we can move down halfway through the second subheading in section three we see
00:31:58 we see an area called drawings and documentation to be referred to do you see that
00:32:04 see that yes and just to clear it up the first document referred to in that list
00:32:11 list herefordshire council type approval summary revision one third of march 2008 that date i think you've explained in your witness statement is a typographical error
00:32:22 typographical error isn't it yes it is there was no earlier type approval summary no no that is in fact a reference to your type approval summary from 2009
00:32:37 to your type approval summary from 2009 that's right yes yeah all right so the two
00:32:40 two documents we're left with are kingspan publication cool firm k15 rainscreen board eighth issue november 2008 and the bba certificate 084582 dated the 27th of october 2008. yes
00:32:55 dated the 27th of october 2008. yes yes if we can go on please to page three there's actually a blank page at page two so if we can go on to page three this is the type approval summary
00:33:06 approval summary yes yes and just to be clear these the wording in this summary all of it is yours yes yes
00:33:17 all of it is yours yes yes right we see there a section at the start called overview which describes the product would you agree yes and then below that
00:33:28 would you agree yes and then below that are heading the system
00:33:32 we can scroll down a little bit please i'd like to look at the whole of that section the system so you say here in the opening paragraph the overall wall construction
00:33:43 the overall wall construction must reflect standard design details as shown in figures one two and three of kingspan technical literature cool firm k-15 rain screen board eighth issue
00:33:54 issue november 2008 the standard forms of construction contained therein and as considered under this system approval would consist of and then you have four bullet points
00:34:07 of and then you have four bullet points am i correct in thinking that what you have done there is explained what can be seen in figures one two and three
00:34:14 three within kingspan's marketing literature yes if we look at the fourth bullet point please a rain screen cladding weathering layer
00:34:25 a rain screen cladding weathering layer structurally fixed back to the inner substrate
00:34:28 substrate and so on those first words a rain screen cladding weathering layer could be taken to mean any rain screen
00:34:39 could be taken to mean any rain screen cladding do you agree
00:34:42 it could although i think further on in the document limit that to a fire performance of limited combustibility yes
00:34:54 of limited combustibility yes and in fact at the first bullet point you've specified from kingspan's marketing literature that the inner substrate needs to be reinforced concrete masonry
00:35:05 needs to be reinforced concrete masonry or hollow metal framed walling forming part of the building's superstructure yes yes can we go on to the fourth page and to the heading requirement b
00:35:26 yes so if we look at requirement b fire safety considerations we see that the words k15 has been tested in accordance with and you then list four test methods
00:35:39 and you then list four test methods eight four one four part one one three six four one and bs476 parts six and seven and under that we see this sentence from the results it can be considered
00:35:51 the results it can be considered as a material of limited combustibility and
00:35:54 and meets the criteria for class naught classification for surface spread of flame just to be absolutely clear you had not at any time seen the test results to which you are
00:36:07 seen the test results to which you are referring
00:36:08 referring the reader there had you no i know i'd copied those out of the bba certificate i believe
00:36:15 and just looking quite strictly at the wording you have used from the from the results it can be considered which of the test standards listed in
00:36:28 which of the test standards listed in that section did you consider gave a result that could lead to the class naught classification you cited
00:36:38 did you know no the class the class naught classification was simply repeating what was stated in the bba certificate but d did you know at the time or do you
00:36:49 but d did you know at the time or do you know now
00:36:50 know now whether any of those test standards can lead to that classification i don't believe i i knew fully at the time um but i i do know now that that the reference to
00:37:02 i do know now that that the reference to class
00:37:02 class naught was was misplaced both on the bba certificate and repeated here or i believe it to be i'm not you believe it to be misplaced
00:37:13 believe it to be misplaced i i don't believe the test results listed there um are able to to give a class norm classification i i might have used the wrong phrase there are no
00:37:24 used the wrong phrase there are no actual test results listed there these are
00:37:26 are simply the test standards aren't they sorry the test standards yes i'm not correcting i'm correcting myself all right looking at the same wording from the results it can be considered which of the test standards listed there
00:37:39 which of the test standards listed there did you consider gave a result that could lead to the material being one of limited combustibility
00:37:47 i think the key one was the bs8414 where where it has been told that here here we
00:37:54 here we we've put this product into a into a system test where uh only limited combustibility will suffice and it's so as far as those test standards go it
00:38:06 so as far as those test standards go it would be the first one the s8414 although it that wasn't the only thing that led me to the limited combustibility wording it was a range of
00:38:16 range of a range of factors that that i took as a whole
00:38:19 whole to make a judgment yeah yes we'll come on to those factors by the time
00:38:26 the time this certificate was issued had you looked up
00:38:30 looked up or read any one of those test standards
00:38:34 no if we go on to page five now please
00:38:44 yes at the top there's a section entitled requirement before external fire spread and i'm going to re read that with you the first paragraph certainly since k-15 can be considered a material
00:38:56 since k-15 can be considered a material of limited combustibility it is suitable for use in all situations shown on diagram 40 of approved document b
00:39:03 b volume 2 including those parts of a building
00:39:07 building more than 18 meters above the ground in the latter circumstances the cladding system and the substrate to which the insulation is applied must also meet the requirement for
00:39:18 must also meet the requirement for limited combustibility where the substrate is a metal frame wall system rather than masonry or concrete and non-combustible lining board must be specified to the external face
00:39:31 must be specified to the external face of the metal frame wall e.g calcium silicate board or similar
00:39:40 performing essentially you're repeating there what you had said to
00:39:51 mr harrison in your email of the 14th of january 2009. and what i mean by that is that since k-15 can be considered i think this is what you mean since k-15 can be
00:40:03 what you mean since k-15 can be considered a material of limited combustibility and because you're extending this to be some sort of system approval
00:40:13 it is suitable for use over 18 meters as long as all the other components of the external wall arrangement are also materials of limited combustibility is that what you intended this to mean
00:40:25 is that what you intended this to mean yes i believe so yes right
00:40:31 yes right can we go please to page 35 of your first witness statement and we're going to go through now the fractures
00:40:40 fractures which you have set out which led you to form a judgment that this was a material of limited combustibility
00:40:49 yes the question is at question 57 which test results in specific terms led to the assertion that k-15 can be considered a material in limited combustibility and you start that by saying as building
00:41:01 and you start that by saying as building control surveyors we were conditioned and expected to gather evidence and use our judgment when considering the compliance or otherwise of building work yes yes when assessing the
00:41:14 yes yes when assessing the combustibility of k15 i considered each of the following and we'll start with a you say that the claims about the material and its properties discussed in the initial meeting
00:41:25 initial meeting with kingspan now i think we've dealt with that meeting in some detail now are you able to assist any further as to which claims made in
00:41:36 any further as to which claims made in the meeting specifically influenced your decision that k-15 could be considered to be a material of limited combustibility
00:41:48 material of limited combustibility it's the the the claims from that meeting that uh the bs8414 test pass has been achieved because of k-15s
00:42:01 pass has been achieved because of k-15s combustibility characteristics as in you know when put in that system it did not bill or did not burn to any great degree uh to cause a risk so
00:42:11 so it was that claim that i was referring to in bullet point a thank you going on to b your second factor is
00:42:20 factor is the statement on the first page of the bba certificate behaviour in relation to fire the boards will not contribute to the development stages of a fire or present a smoke or toxic hazard just
00:42:32 or present a smoke or toxic hazard just to put it in context let's get that up please it the document is bba
00:42:38 bba 6038 and we need to go to page one
00:42:48 yes so if we just uh identify this this is bba certificate 084582 and if you look to the left-hand bottom corner we can see that it's dated the 27th of october
00:42:59 27th of october 2008. do you see that yes i think we can agree can we that this is the one you saw at the time of your assessment yes it is right
00:43:10 yes it is right looking at this page do you see under the heading key factors assessed there are four factors listed in both and the fourth is behavior in relation to fire
00:43:22 and i think that is the phrase you're referring to at your paragraph b in your witness statement we've just looked at the boards will not contribute to the development stages of a fire or present a smoke or toxic hazard
00:43:34 present a smoke or toxic hazard yes yes
00:43:37 i understand your evidence is that this particular assertion formed part of your consideration in forming your judgment as to the combustibility or otherwise of the product can we go
00:43:48 or otherwise of the product can we go back please to page 45 of your first witness statement where separately you were asked about this particular assertion in the bba certificate yes it's an inquiry question 78
00:44:02 yes it's an inquiry question 78 you were asked about the meaning of it and you said i took this to mean that the k-15 boards were not capable of burning to an extent where they could contribute towards the development or spread of a
00:44:13 towards the development or spread of a fire this was one of the statements which led me to conclude that k-15 was of limited combustibility yes yes was this particular factor and
00:44:26 yes yes was this particular factor and that assertion in the bba certificate something you ever considered taking any advice on or did you consider it to be sufficiently clear
00:44:37 sufficiently clear it was quite a direct statement and i took it
00:44:41 took it as as as it reads it was quite it was very significant to me at that time in terms of this judgment on the combustibility of the product very similar very significant i'm so sorry i just spoke to you go
00:44:52 i'm so sorry i just spoke to you go ahead sorry yes it was very significant and i think without without that statement i don't think the other factors i considered would have been enough to to make that the judgment has to limited
00:45:04 the judgment has to limited combustibility i see so this is the one that sort of swung the balance towards limited combustibility was it yes yes all right going back to your
00:45:15 yes yes all right going back to your list of factors in your witness statement at page 36
00:45:26 if we look at c and d i'd like to take those together because they go together if i read those to you
00:45:34 to you you say the fact as stated in both the bba certificate and the kingspan literature that the product had been successfully tested to bs 8414
00:45:43 bs 8414 it would have been my view at the time that the insulation board would have to be a material of limited combustibility to pass such a test and then that's essentially repeated in d
00:45:54 essentially repeated in d in respect of br135 do you see yes great
00:46:01 yes great so as far as i know as far as i understand from your evidence thus far although you use the plural there in the
00:46:12 although you use the plural there in the second line of paragraph d you were aware i think that only one test to 8414 had been carried out on a system incorporating k-15
00:46:23 incorporating k-15 yes i believe that you'd be right yes and you understood that bs8414 was a system test not a product test yes
00:46:37 i think you said earlier that you had not understood at the time that it was a system test meaning that every component these were not your
00:46:49 every component these were not your words i'm summarizing but i think you said you had not understood that every component part or the system and every part of it would have to be replicated exactly in order to be used in compliance
00:47:03 in order to be used in compliance with approved document b is that right that's right yes when did you come to understand that the system had to be replicated exactly
00:47:14 uh in the last um 16 months while while reviewing the matter for this inquiry yes
00:47:25 the matter for this inquiry yes all right i want to ask you now about the second sentence which is mirrored at paragraph c and d it would have been my view at the time that the insulation board would have to be a material of limited combustibility
00:47:36 material of limited combustibility to pass such a test and we've referred to this a few times in terms of the meeting that you had with kingspan i just want to be absolutely clear what do you mean by that sentence
00:47:48 do you mean by that sentence the insulation board would have to be a material of limited combustibility to pass such a test i think it links to what i was saying of my impression uh from kingspan at that meeting
00:48:00 that meeting that uh this principle that that the product had been put into a test situation where a limited combustibility material would be a requirement would be the minimum requirement and it's fast it's behaved as as it would be
00:48:12 it's fast it's behaved as as it would be expected to be so i think after that meeting it that gave me the view that uh it it must
00:48:23 that uh it it must perform equally to a material of limited combustibility in order to have passed the bsa414 test uh now
00:48:30 uh now i would draw a slight distinction between what you've said there it would have to perform equally to a material of limited combustibility and the wording in your statement do you
00:48:41 and the wording in your statement do you mean
00:48:43 mean i just want to be absolutely clear on this do you mean that you understood that in order to pass a test to 8414 the board would have to be of limited
00:48:55 the board would have to be of limited combustibility or are you saying as i think you've just said that it would have to perform equally to a material of limited combustibility
00:49:06 they're not quite processed sorry i'm so sorry i said they're not quite the same are they do you see they're not quite the same no you're right i i'm not sure my thought process at that time
00:49:17 sure my thought process at that time would have drawn the distinction between the two
00:49:20 the two um but i think if if you look at the way i've written at that time in in my report to labc i've allowed
00:49:31 i've allowed that view to to to result in the conclusion that that it can be treated as a limited combustibility material not that it's like
00:49:41 like a material of limited combustibility give me a just to make sure that i haven't misunderstood i i i'm not sure you say in in the certificate it can be treated as a
00:49:52 certificate it can be treated as a material of limited combustibility do you i think you say it can be considered to be one yeah yes yes that's right i did we spoke earlier about the fact that you
00:50:03 about the fact that you um referred during your work on this assessment to approve document b and in particular to
00:50:10 to um section 12 i think i want to take you to that please if we can go to clg 1607
00:50:22 to clg 1607 and to page 95 mr jones this is approved document be as it stood at the time that you were carrying out your assessment not not as it stands now
00:50:35 so i'm sorry it's yes i think it's coming up
00:50:39 coming up yes if we look on the right hand side of the page towards the bottom under the heading external wall construction that's paragraph 12.5 we see there the following wording the
00:50:51 we see there the following wording the external envelope of a building should not provide a medium for fire spread if it is likely to be a risk to health or safety the use of combustible materials in the chatting system and extensive cavities may present such
00:51:04 and extensive cavities may present such a risk in tall buildings external walls should either meet the guidance given in paragraphs 12.6 to 12.9 or meet the performance criteria
00:51:16 to 12.9 or meet the performance criteria given in the bre report br135 for cladding systems using full-scale test data
00:51:24 test data from bs8414.1 or part two yes yes
00:51:32 so keeping that wording in mind external walls should either meet the guidance in 12.6 to 12.9 or meet the performance criteria in br135
00:51:43 br135 can we go over the page please to page 96
00:51:47 96 within adb and to paragraph 12.7 and we can see that that is the relevant paragraph for insulation materials yes yes in a building with a story 18
00:52:01 yes yes in a building with a story 18 meters or more above ground level any insulation product filler material not including gaskets sealants and similar etc used in the external wall construction
00:52:12 used in the external wall construction should be of limited combustibility see appendix a and what i want to ask first is this did you read these two sections
00:52:23 you read these two sections at the time you were carrying out your work on this assessment
00:52:28 i did yes would you agree with me then that it is clear that these two routes if i can put it in that way are alternatives
00:52:39 are alternatives either the material is one of limited combustibility or it meets the criterion br135 yes i can i can see that that is the
00:52:50 yes i can i can see that that is the case
00:52:51 case did you see that that was the case at the time
00:52:55 the time i i've i've looked at this repeatedly over the last um 14 months and tried to recreate my thought process when looking at this
00:53:06 when looking at this and
00:53:09 i find it difficult to recall how i interpreted it at the time um i think i can only i can only say that i'd never used this section of approved
00:53:21 i'd never used this section of approved document b before because it related to a type of building and a situation that had never come up for me previously yes and and i would certainly not go about it in the same way again
00:53:33 about it in the same way again but at the time
00:53:36 i i'm not sure i had that i wasn't on the right track with it i would say all right can i take it that you did not realize
00:53:48 can i take it that you did not realize at the time that they were alternatives
00:53:53 i i think i realized from the word or would have realized from the wording of it that that's two alternative approaches but i think it appears as if i've mixed
00:54:04 it appears as if i've mixed mix and matched a bit there in terms of the limited combustibility term which which i agree was was not the right way to go about it all right we'll come on to that i mean
00:54:16 all right we'll come on to that i mean in
00:54:17 in layman's terms from reading 12.5 taken together with 12.7 it it if you are clear now that those
00:54:29 it it if you are clear now that those are posed in the alternative so either the material is one of limited combustibility or you meet the criteria in br135 by testing to bs8414
00:54:41 testing to bs8414 it follows doesn't it that if k15 was a material of limited combustibility there'd be no need to test it to the s8414
00:54:50 s8414 no that would be right did that occur to you at the time
00:54:57 i i'm not sure quite how i thought about it at the time i i think it would have done in that i would have i would have been able to read those paragraphs and understand them at the time just
00:55:08 and understand them at the time just wasn't used to applying them in in real world situations i see all right let's go back to your list
00:55:19 list of factors in your witness statement if we can go back to page 36 please and to paragraph e
00:55:34 page 36 please and to paragraph e so this is the next factor that contributed towards your decision to uh assert that the product was one of limited combustibility and you say there the statement in section seven of the
00:55:45 the statement in section seven of the bba certificate that the product displayed limited fire spread away from the source so let's go back and look at that please it's bba6038
00:56:06 we need to go down to page five to section seven
00:56:13 the heading there is behavior in relation to fire do you see it yes it's quite tricky to find but if you go to the
00:56:23 end of the the first quite big paragraph to the the final three lines the third line up from the bottom beginning within
00:56:34 beginning within i think that's where that phrase comes from within the stated test time the temperature at the level two thermocouples did not exceed 600 degrees therefore displaying limited fire spread away from the fire source
00:56:46 fire spread away from the fire source and that the product meets the criteria stated within the r135
00:56:51 r135 that is the phrase you're referring to in your factor e is it yes yes so that is contained within
00:57:00 within a description there of the way in which the system tested to bs 8414 is said to have met the criteria
00:57:08 criteria in br135 yes while we're on this section this makes clear does it not this part of the bba certificate that there's one test to bs8414
00:57:21 there's one test to bs8414 yes and that is to part one yes when you saw that did it prompt you to look up
00:57:31 look up either part one or part two or even a summary of the differences between them
00:57:38 i don't believe it did uh i believe i was led by the the comment in in in the uh third line down actually the first line where it refers to a non-combustible
00:57:49 where it refers to a non-combustible substrate and i think that that led my thought process to a more generic non-combustible substrate being the parameter of this test yes and as far as i understand it from your evidence that accorded with what
00:58:01 your evidence that accorded with what you were told by kingspan when you met with them did it it did and and this was a big part of um of the process for me that when i came away from the meeting what i was seeking to do was go back to
00:58:12 what i was seeking to do was go back to the bva certificate and see if the statements and the impression i'd been given in the meeting could be supported by the bba certificate and this was one of the
00:58:20 of the one of the phrases that led me that way and said yes okay that is consistent with what kingstown was saying yes i see this
00:58:28 this appeared to be appeared to you on review to be consistent with what either andrew pack or philipp heath or both had told you yes that's right i see all right
00:58:40 yes that's right i see all right can we go back to your witness statement now page 36 and to your uh factor at f
00:58:49 you say there the reference in section 7 of the bba certificate to a bsdn1364 part 1 test where an assembly containing k-15
00:59:00 where an assembly containing k-15 achieved a fire resistance of 53 minutes it would have been my view at the time that the insulation board would have to be a material of limited combustibility to pass such a test to this standard
00:59:13 to pass such a test to this standard i don't think we need to go back to that in the bba certificate i just want to ask you this on what basis
00:59:20 basis did you determine that the result of a fire resistance test of bsen 1364 part 1 could tell you anything at all about the
00:59:31 could tell you anything at all about the combustibility of a product um i don't think it didn't directly uh i think the the paragraph f was just background information it was
00:59:42 was just background information it was just another piece of evidence in the background that suggested this this insulation it didn't readily burn as i've been given to understand
00:59:53 given to understand so i understand that the test standard referred to there had no relevance it wasn't mentioned at all in section 12 of approved document b but it was it was just in terms of gathering as much
01:00:04 just in terms of gathering as much evidence as i could to try and make a judgment it was just another bit of background information i see moving on to g then you say there i think this might be the
01:00:16 you say there i think this might be the last one
01:00:17 last one the suggestion in paragraph 7.2 of the bba certificate that k15 could be suitable for use with stories over 18 meters if the certificate holder kingspan
01:00:28 certificate holder kingspan were to say so and the subsequent statement from kingspan in their technical literature saying so that k-15 is therefore acceptable for use above 18 meters in accordance with the building
01:00:40 meters in accordance with the building regulations i want to take a look with you please at the product literature that was provided to you by kingspan that is at kin409703
01:01:00 the title of that uh piece of literature is cool phone k-15 rain screen board insulation for use behind rain screen chatting systems and if we can just zoom in a little bit
01:01:12 and if we can just zoom in a little bit on the top right hand corner please
01:01:18 we can see that that is the eighth issue dated november 2008 yes yes moving to page six please
01:01:32 if we look at the section it's on the left hand side about halfway down entitled fire performance
01:01:40 there in the smaller letters still even smaller letters we can see four test standards listed on the left and result on the right yes
01:01:51 on the left and result on the right yes yes
01:01:53 yes and under that we see this so under those four test standards and results
01:02:00 results uh we see the following assertion kingspan call firm k15 rain screen board meets the criteria within br135 fire performance of external thermal insulation for walls of multi-story
01:02:12 insulation for walls of multi-story buildings
01:02:13 buildings and is therefore acceptable for use above 18 meters in accordance scroll up a little bit please
01:02:23 or scroll down a little bit i mean
01:02:30 in any event in accordance with the building regulations and standards is that the section to which you were referring in your witness statement um yes i have referred to that
01:02:41 referred to that that paragraph uh which i think that was whether consciously or not uh instrumental in leading me towards the combustibility
01:02:53 the combustibility approach because i suppose there's only one way
01:02:57 one way that kingsman could make such a blanket statement about about the product and that is to link the quote link it to the performance of the product rather than the system um because that
01:03:08 rather than the system um because that is a blanket statement now we're in that document does it say actually that only applies in in certain very limited circumstances and i think perhaps in my mind i was trying to rationalize that to say i actually
01:03:19 rationalize that to say i actually in order to say that you've got to be prepared to to to um allocate some characteristics to this product what how can this product be
01:03:31 how can this product be suitable for use in situations above 18 meters on a blanket basis like that unless we're talking about the combustibility properties of the product yes can we go
01:03:43 properties of the product yes can we go back to that document please uh kn409703
01:03:49 when you say blanket statement that statement we've just looked at is therefore acceptable for use above 18 meters
01:03:56 meters i think this is what you referred to earlier it contains no caveat or qualification does it no it doesn't you know i find it very misleading now when i read it back knowing the background to it i see
01:04:10 knowing the background to it i see can we go up please to page two i want to look with you at the diagrams we discussed a little earlier um which you refer the reader of your type
01:04:21 which you refer the reader of your type approval
01:04:22 approval summary directly to do you remember yes yeah so if we look at those please i think you said in relation to these and we can go back and check it if not
01:04:33 and we can go back and check it if not that you saw these and understood them to be standard design details again with no caveat or qualification as to any height restriction in terms of
01:04:45 as to any height restriction in terms of how they should be installed is that right that's right we see these diagrams alongside that statement that k-15 is suitable for use over 18 meters no
01:04:54 meters no no qualifications no limitations and so i think it's very misleading to put those diagrams there and then and then read those alongside the bba certificate describing a non-combustible substrate
01:05:06 non-combustible substrate which which you have in each of those three diagrams and under limited combustibility cladding um panel which again i believe we have in those three diagrams so everything about those diagrams seems
01:05:18 so everything about those diagrams seems to lead you towards the 18 meter paragraph and and it left me with the impression that these three diagrams were all within the parameters of the test that uh that
01:05:29 the parameters of the test that uh that that allowed kingspan to claim the 18 meter
01:05:32 meter suitability on the basis that there is nothing
01:05:36 nothing there to say that these fall outside the parameters of that test that's right yes so did you examine these diagrams and the wording around them
01:05:47 the wording around them during your assessment i would yes i would have examined them and looking at the key factors as in the combustibility of the substrate and the declining panels
01:05:58 substrate and the declining panels yes all right can we go uh back now please to the bba certificate bba
01:06:11 now please to the bba certificate bba 6038
01:06:15 and again to page five section seven
01:06:28 thank you if we go in fact i'm so sorry down to page six and to section 7.3
01:06:38 here we see the bba advising as follows in buildings with a floor more than 18 meters above ground level advice should be sought from the certificate holder is that what you were referring to mr
01:06:50 is that what you were referring to mr jones
01:06:51 jones when you said in the section of your statement that we've just looked through the bba certificate says that it's okay for use over 18 meters if kingspen were to say so
01:07:02 to say so that's right yes yes this refers you to kingston and of course i was i was talking to kingspan about this so so yes
01:07:13 did it strike you at the time as all a bit circular the kingspan cite their bba certificate and when you go to the bba certificate if you're looking to use the product
01:07:24 if you're looking to use the product over 18 meters you're directed back to kingspan
01:07:27 kingspan yes i'm not sure if it did at the time but it certainly does now yes all right can we go back to your witness statement pleasing to page 36 i'm afraid i'm
01:07:39 36 i'm afraid i'm i was wrong there is one more fracture that we need to take a look at there which uh contributed towards your judgment that the product was one of limited combustibility and that's
01:07:51 of limited combustibility and that's this that's at h the assertion in both the bba certificate and and the kingston literature that k-15 is classified as a class naught product not in itself evidence of limited combustibility as discussed under a
01:08:03 combustibility as discussed under a previous question but another piece of evidence which viewed alongside all of the above would have helped support the judgment that it was yes yes
01:08:15 in what way did you determine that a classification to class naught helped support a judgment that a product was one of limited combustibility
01:08:26 um only to to link to one of my previous um
01:08:29 um answers where i talked about classo products having a surface material that that would more often not be of limited combustibility
01:08:41 limited combustibility the very the very feature that allows it to pass a test to class class naught and the fact that in the case of k-15 it's a solid block
01:08:53 in the case of k-15 it's a solid block of insulation so the material that has achieved class naught on the surface is the same material all the way through and again this this is not this is not a direct link to limited combustibility but it's
01:09:05 link to limited combustibility but it's another piece of background information when i'm when i'm gathering the evidence to try and make a judgment one way or the other it's another bit of background information that pushes me to towards the conclusion i made all right
01:09:21 towards the conclusion i made all right i just i want to ask you uh something else about h i notice in the final line of that paragraph that you use uh the word would would have helped support the judgment that it was
01:09:33 support the judgment that it was and in fact i think you've used that in some of these other factors that you've set out for us it may just be the way that it's been phrased but just say that i'm here is it your evidence that you considered
01:09:46 is it your evidence that you considered at the time each of these factors that you've listed here in your witness statement at a to h or is it on having been asked about it that you have thought it
01:09:58 about it that you have thought it through
01:09:59 through in this way no i i i recall looking at each of those uh each of those examples listed at the time and and using them all to make a judgment
01:10:12 i see all right can we go uh i'm going to look with you at the under h the next paragraph and just read from there on the basis of my knowledge at that time
01:10:23 at that time the range of evidence in a to h above was sufficient for me to make a judgment that k-15
01:10:29 that k-15 could be considered a material of limited combustibility i was aware that if defined as a material of limited combustibility it could in principle be used in stories
01:10:41 it could in principle be used in stories over 18 meters in accordance with paragraph 12.7 of approved document b but i was being told by the bba certificate and the kingspan literature that k15 had met the criteria for br135
01:10:55 that k15 had met the criteria for br135 so had already been proved to be suitable for stories over 18 meters in any case and going over please to page 37
01:11:13 yes at the top there my type approval summary to labc was only confirming something which was supposedly already known yes yes
01:11:25 yes yes basically is this right you thought at the time that you were saying nothing new in your approval by calling this material one of limited
01:11:36 by calling this material one of limited combustibility that is right i thought i was simply representing the information i'd been given
01:11:42 given uh both both verbally from kingston and in the documents they they gave me i i honestly didn't uh appreciate at that time that using the
01:11:54 appreciate at that time that using the words limited combustibility was was opening any doors for kingsman that hadn't already been opened by the information that was already available
01:12:03 available i see when did you come to appreciate that using the words the specific words a material of limited combustibility would have the effect that you've just
01:12:15 would have the effect that you've just described
01:12:17 described um i don't think i had cause to revisit in that in that context in that detail until i was asked to um contribute to the inquiry
01:12:28 the inquiry in 2019
01:12:31 mr jones did it not strike you as odd if that is the case forgive me if that is the case and you were saying nothing new
01:12:42 nothing new and k-15 was a material of limited combustibility did it not strike you as odd at the time that neither the bba certificate nor kingspan's own
01:12:53 the bba certificate nor kingspan's own product literature said so
01:12:57 um i think perhaps i put a lot on that statement on the page one of the bba certificate that appeared to me to be saying to be to be describing
01:13:11 to be saying to be to be describing uh a material that had a limited capacity to burn i made the link from that to limited combustibility fine did you notice that neither the bba
01:13:24 fine did you notice that neither the bba certificate nor king spanzone product literature anywhere made the claim that k-15 was a material
01:13:31 material of limited combustibility or could be considered to be one i think i probably did but as as i've said previously i i don't think
01:13:43 as i've said previously i i don't think at that time i was making a clear enough distinction between
01:13:47 between the specific phrase limited combustibility and a product which had a limited capacity to burn
01:13:54 to burn i i i understand now that that's two very different criteria but i don't think i understood that at the time so the fact that the specific phrase limited combustibility wasn't
01:14:05 phrase limited combustibility wasn't used
01:14:06 used i i don't think it registered with me as as being significant at that time i see and at the time you made your judgment
01:14:17 and at the time you made your judgment on the basis of the matters we've just been through in some detail and you considered at the time that your judgment was sound is that right yeah i did yes yes
01:14:29 is that right yeah i did yes yes right and i was also aware of course that this was just the first stage and and that this would go forward for further checking and verification yes can we just uh go back
01:14:42 yes can we just uh go back please to your witness statement at page 33.
01:14:45 33. i want to just look again with you at your answer to what your understanding was as to the meaning of the phrase limited combustibility in may 2009
01:15:05 not sure that is the right page actually just bear with me for a moment
01:15:15 yes actually let's look at that section you say there in response to question 52 i had made a judgment based on the range of statements and test results referred to in the documents reviewed that the product had a limited capacity
01:15:27 that the product had a limited capacity to sustain fire and was therefore limited in its combustibility
01:15:36 you've just explained that you did not appreciate at the time the distinction between those two things just to be absolutely clear with you were you aware in
01:15:49 were you aware in late 2008 and early 2009 that the words of limited combustibility have a defined and specific meaning within approved document b
01:16:01 meaning within approved document b yes i knew of the reference in in document b and appendix a yes i thought you said to us earlier you must correct me
01:16:12 earlier you must correct me if i'm wrong but i thought you said to us earlier that it was from your analysis after the grenfell tower fire that you had come to understand that there was a specific
01:16:24 that there was a specific and defined meaning for those words now i knew of the appendix a definition in the approved document from having read section 12 during
01:16:36 from having read section 12 during my my assessment of of this product in 2008.
01:16:40 2008. i see but but in section 12 i think you're talking about 12.7 it simply says in brackets appendix and that you're aware that there existed a definition or did you know what it was i i knew
01:16:53 or did you know what it was i i knew that there existed a definition but but i i i would have been very much in a frame of mind at the time that that's that's an approved document definition but there may be other ways
01:17:04 definition but there may be other ways of proving that the functional requirement and i think that that's key to how
01:17:10 to how i was trained to to think as a building control
01:17:13 control officer to to read requirements in an approved document but not just
01:17:20 not just to reel them off of their patent to understand why they were asking for what they were asking for so in in 12.7 i asked myself why is approved document
01:17:32 i asked myself why is approved document be asking for limited capacitability what's what's the end
01:17:37 end objective of that and of course it is to make sure that the installation product can't contribute to the development of a fire and then of course i come back to
01:17:48 and then of course i come back to the statement on page one of the bba certificate which tells me actually it does it does achieve this aim
01:17:55 aim so not via the definition in appendix a but
01:17:59 but via a more functional definition that says this insulation will not contribute to the spread of fire
01:18:08 i'm not sure i follow we'll come back to some of the substance of what you have just described in terms of your process of thinking but in very basic terms is what you're saying this you were aware from paragraph 12.7 that
01:18:21 you were aware from paragraph 12.7 that there
01:18:21 there existed in appendix a a definition of the phrase limited combustibility yes you did not look that up and were not aware of
01:18:32 aware of what that definition was
01:18:35 i believe i probably referred to it i believe i probably did look it up disregarded it you i'm so sorry did you say disregard i wouldn't have disregarded it i would
01:18:46 wouldn't have disregarded it i would have looked i i believe i would have looked it up having having seen it referred to in paragraph 12.7 i see so you saw it referred to in 12.7 you went to appendix a and then you
01:18:58 you went to appendix a and then you decided
01:18:59 decided based on your training um and different ways to meet the functional requirements of the building regulations that you would give it an alternative definition is that what you're saying
01:19:10 definition is that what you're saying that's
01:19:11 that's that's right that that i've seen at the other statements and in particular that statement on the first page of the bba certificate that indicated to me that the functional requirement we would be looking for in
01:19:22 requirement we would be looking for in an installation panel i.e that it not contribute to the spread of a fire is in in the opinion of the bba
01:19:28 bba achieved because they they say so in that statement albeit that it doesn't use the specific phrase limited combustibility yes i i think i follow what you're saying i'm
01:19:39 i think i follow what you're saying i'm just i'm going to come back to this i'm afraid
01:19:43 afraid you say that you did uh go to appendix a and decided to come up with an alternative definition than the one you found there for a material limited combustibility
01:19:56 i'm not sure that i'm clear on why you did that
01:20:04 did that i think it was just a case of gathering the evidence i had uh and i'm saying okay there isn't a test report that links to the definition of a
01:20:15 that links to the definition of a limited combustibility that is in appendix a but there is there are other evidence that seems to suggest
01:20:22 suggest that it achieves that functional requirement that appendix a is trying to ensure
01:20:30 did you not consider that you might be taking quite some risk in unilaterally deciding to step outside of the definition that is set out for you in approved
01:20:41 that is set out for you in approved document b and coming up with an alternative one well i think stepping outside of the strict criteria of the approved documents was it was was an established
01:20:53 documents was it was was an established practice in building control then it was it was almost expected of us you know that we'd be prepared to look at alternative solutions uh in any given situation
01:21:02 situation um in terms of whether i thought it was a risk i think i probably read a great deal into the statement on the bba certificate in terms of you know how this how this product
01:21:12 product performs when when put in a fire situation
01:21:15 situation the statement on the first page that the boards will not contribute to the development stages of the fire yes all right i i think i follow to some extent
01:21:25 extent uh and you must forgive me what you're saying about almost being expected to step outside of the approved document criteria because and to come up with
01:21:37 because and to come up with alternative ways of meeting the functional requirements i think i follow what you're saying i'm not sure that i follow that in relation to stepping outside of defined terms specifically defined
01:21:50 of defined terms specifically defined phrases that is surely a different matter wouldn't you say um
01:21:57 perhaps looking at it now yes um but at the time it was it was such an established practice that it is okay to put the approved document to one side and look at other evidence that
01:22:07 that i just think that's what i was doing at the time
01:22:11 the time the difficulty i mean did it occur to you
01:22:14 you that you were not on this occasion stepping outside of the confines or the language of approved document b on one building project you were certifying a product which might go on
01:22:28 certifying a product which might go on to be used in hundreds upon hundreds upon hundreds of building product projects and stepping outside the defined criteria
01:22:39 stepping outside the defined criteria of a material of limited combustibility to do so you were taking an enormous risk weren't you um i suppose i didn't
01:22:51 um i suppose i didn't see it that way at the time because i knew that every every actual building that was built would go through a full design and statutory approval process you know regardless of this
01:23:02 you know regardless of this labc certificate um that every every building would be improved on its own merits as a as a bespoke um design so
01:23:14 um design so there were other layers of of um
01:23:19 other layers of checking that would that would ensure it was it was used appropriately yes all right can we go please to appendix a and specifically to table a7
01:23:31 table a7 we'll find that at page oh sorry i should give the document first that's clg 1607 yes 1607 and i'd like to go to page 121
01:23:46 please
01:23:58 uh so down a couple of paid o yes i see all right so if you look on the right hand side under the heading materials of limited combustibility
01:24:10 we see there materials of limited combustibility are defined in table a7 yes yes do you think you looked at this
01:24:21 yes do you think you looked at this i i believe i would have yes i i know because it was referred to in paragraph 12.7 all right so let's go to table a7 please which is on page 132 of this document
01:24:39 and if you look thank you on the left hand side of table a7 we see sort of three rows down the words references in adb guidance to situations where such materials should be
01:24:51 materials should be used yes yes and then if you follow that column down if we scroll down please to number eight
01:25:02 we can see this specific situation insulation material in external wall construction referred to in paragraph 12.7
01:25:14 referred to in paragraph 12.7 yes yes and then in the right hand column
01:25:18 column we are given if we go scroll back up please
01:25:25 we see the definition of materials of limited combustibility is given to us for national class in the in the left-hand section and if we go back down i'm so sorry to
01:25:36 and if we go back down i'm so sorry to number eight we can see there that what can be defined as a material of limited combustibility for this situation is any of the
01:25:49 for this situation is any of the materials in a b or c above and i'll come to those or d
01:25:54 d any material of density less than 300 kilograms
01:25:58 kilograms it goes on which when tested to bs 476 part 11. so rather than reading that any further it is right i think that no one had suggested to you that
01:26:10 that no one had suggested to you that k15
01:26:11 k15 had at any stage been tested to bs 476 part 11 had they no you had seen no reference to a test to that part of bs476
01:26:22 to that part of bs476 no so k15 cannot fall within d would you agree with me let's go up please to look at a b and c
01:26:35 we just scroll up we'll come back to a because it's going to take us to another table
01:26:41 table b again this is a reference to particular results following a test of bs 476 part 11 and you've just agreed that you saw no reference to k-15 being tested to that
01:26:52 reference to k-15 being tested to that section
01:26:54 section yes yes so it can't fall under b can it no
01:27:01 can it no and at c we see a description any material with a non-combustible core at least eight millimeters thick having combustible facings on one or both sides it goes on
01:27:12 both sides it goes on k-15 is not a material described there is it
01:27:16 is it no it's not right so we're left with a let's go up please to table a6 at page 131
01:27:27 and here we come to four more options a b c and d
01:27:31 b c and d if we can deal first please with a and d again in a you're asked to look at particular results to bs 476 part 11 and you knew of no such tests
01:27:45 part 11 and you knew of no such tests is that right that's right yes so we can scrap that one it can't k-15 cannot fall under a looking at d please products classified
01:27:56 looking at d please products classified as non-combustible under bs476 part four you had seen no indication of any testing at any stage to part four of bs476 on k15 had you
01:28:10 to part four of bs476 on k15 had you yeah right so it can't fall under d either and we're left with b and c b refers to totally inorganic materials such as concrete fired clay ceramics
01:28:22 concrete fired clay ceramics it goes on k-15 is not one of those materials is it no and we're left last with c concrete bricks or blocks
01:28:33 bricks or blocks meeting a particular british standard well k-15 is certainly not either of those things is it no mr jones in the simplest possible terms
01:28:43 terms just following this investigative trail which is set out for you in approved document b rather than piecing together all the bits and pieces of evidence you appear
01:28:54 bits and pieces of evidence you appear to have picked up from the bba certificate and kingspan's own marketing literature is it fair for me to say that had you carried out the exercise we have just carried out
01:29:07 the exercise we have just carried out within the space of about eight minutes you would have concluded that k-15 is not a material of limited combustibility as defined within approved document b
01:29:18 approved document b um as per the document b definition yes i would agree yes did you in truth carry out the exercise
01:29:29 did you in truth carry out the exercise we have just carried out to establish whether or not this material
01:29:34 material meets the definition of non-combustibility in improved document b
01:29:41 i i can't recall but i believe i would have referred to these tables
01:29:47 i'm not sure my now i i can't recall the detailed process i went through um i think i i was
01:29:58 my my judgment was perhaps skewed by the the impression i have what i've been told that but this
01:30:09 what i've been told that but this product had already by virtue of br135 being given the okay to be used over 18 meters so so it was
01:30:19 was like that i didn't believe in terms of the risk
01:30:23 the risk of the judgment i didn't i didn't believe i was saying anything new as i looked at it at that time do you accept mr jones that had you simply followed
01:30:36 simply followed the definitions within approved document b as we have just done you would never have ended up writing in a certificate for k-15
01:30:47 a certificate for k-15 this material can be considered a material of limited combustibility no i would not okay that's correct
01:30:58 do you think it is possible in fact that you simply did not know in late 2008 and early 2009 that limited combustibility carried a
01:31:09 that limited combustibility carried a specific and defined meaning
01:31:14 i think it is possible yes yes but i didn't understand the significance of that
01:31:18 that do you think it's possible that you were unaware that it had a definition with within approved document b uh i because i can't recall how i refer
01:31:30 uh i because i can't recall how i refer to the document all i can say is that i believe that i would have referred to those tables simply because they were referred to in paragraph 12.7 but i but i can't recall how i went about it
01:31:41 about it in that respect so i can't say for certain
01:31:47 all right mr jones i'm going to pause you there for a moment just looking at the time mr chairman i wonder whether this might be an appropriate time for us to take a short break it might be how are you getting on i'm
01:31:59 it might be how are you getting on i'm doing
01:32:00 doing fine for time and this is a good a good point
01:32:03 point as good a point as any
01:32:06 all right well we'll take our mid-afternoon break a little earlier than usual mr jones we'll um come back at half past three please
01:32:16 please and while we're having our break please don't talk to anyone about your evidence or
01:32:21 or anything relating to it all right all right
01:32:24 right there you go thank you very much we'll see you at our street room please thank you very much
01:50:36 welcome back everyone we're ready to continue hearing from mr jones mr jones just check that you can you're there you can see me and hear me yes i can very good ready to carry on
01:50:50 yes i can very good ready to carry on yes yes thank you very much well when you're ready ms troop thank you mr jones i'm going to take you back
01:50:58 back now in time do you remember we looked at an email
01:51:02 an email uh from november 2008 when you first became
01:51:05 became involved in this process and phil harrison of the labc sent to your line manager chris jenner a pdf document called type approval service manual
01:51:17 type approval service manual yes if we can just go please to your second witness statement which is hbc6051 and to page four
01:51:35 and to page four i want to look with you please at paragraph 14 where you're talking about that service manual you say there i cannot categorically say whether i saw the service manual or not at the relevant time
01:51:47 at the relevant time i may well have seen it and a clue to this is that the 500 pound minimum fee i quoted to which i referred in an email to phil harrison of the 14th of january 2009
01:51:59 of the 14th of january 2009 that's the email i was just no that's not the email i was just talking about there's a later one but seems to reflect section four of the guidance yes yes and then if we go over the page please to paragraph 16 oh
01:52:12 over the page please to paragraph 16 oh no down the page i'm so sorry so back up to page four and to paragraph 16 you say there the manual confirms what i was told by labc about accepting
01:52:25 what i was told by labc about accepting the content of the bba certificate without further interrogation and you refer there at the last line to section
01:52:33 section 3.3 of the manual verification yes yes let's go to that please uh it's at hbc 6040
01:52:53 and if we go to page 17 we should find section 3.3 of the manual there we are do you see under the heading verification
01:53:04 verification yes we see there uh the following to ensure compliance particularly in relation to some system and product approvals the scope of assessment will perforce be
01:53:15 the scope of assessment will perforce be wide
01:53:16 wide it should embrace verification of the following and there are then a number of bullet points setting out certain
01:53:23 certain checks or site visits visits or ongoing audits yes yes if we look at the paragraph under those bullet points we see this in the two circumstances marked above
01:53:36 in the two circumstances marked above the holding and submission by the customer of authoritative independent third party verification particularly if it is from a ucas accredited source or other method recommended in approved
01:53:48 or other method recommended in approved document
01:53:49 document seven is likely to indicate an acceptable level of satisfaction for our approval purposes and eliminate the need for any additional checking within that aspect is that the section
01:54:03 within that aspect is that the section to which you were referring
01:54:07 it is yes and and it it it links to what i was uh told verbally by labc when i spoke to them uh in that first telephone conversation
01:54:18 telephone conversation yes can you remember now whether you picked up the advice to accept whatever the bba was saying at face value
01:54:29 face value from your phone conversation or whether you additionally read this document at the time it was sent to you in late 2008. well sent to mr jenner i'm sorry yes my recollection was was
01:54:43 i'm sorry yes my recollection was was being
01:54:44 being told this or discussing this during that telephone conversation but this document was within her future council's possession at that time so it's possible that i'd also read this document at that time
01:54:56 document at that time um and and and that might have prompted me to to ask during the conversation you know what what does this mean
01:55:05 my memory is a little bit fuzzy on that uh when i when i wrote my first witness statement i couldn't remember this document
01:55:11 document although there are elements of it that i now remember being aware of yes all right can we go back now please to your first witness statement
01:55:22 your first witness statement uh hbc60 sorry to interrupt you miss troop but
01:55:25 troop but i'm just curious on this page that we're looking at the uh passage you just referred us to with the double asterisks at the
01:55:36 with the double asterisks at the beginning suggests that there may be some circumstances marked with double estuaries
01:55:42 estuaries where are they it does i'm afraid we haven't been able to discover the answer to that question there don't appear to be any particular sections marked with a double
01:55:52 double astra oh i'm being told i think that it's
01:55:58 ah i think uh mr chairman that that is a reference to section 3.3 itself and to section 3.2 above because do you see that at the end of
01:56:09 because do you see that at the end of the list of bullet points there are two asterisks
01:56:13 asterisks i see that's meant to govern the whole of three three is it it is i think that's the answer i see all right thank you very much
01:56:25 mr jones can we go back please to your first witness statement which is hbc6029 and to page 41.
01:56:45 if we go please to
01:56:50 the fourth paragraph there starting i have no doubt no in fact if we go just above that this is a section we've looked at already
01:57:01 is a section we've looked at already starting in terms of merit do you see it yes and that's where you you um described your views at the time of kingspan a world leader in insulation
01:57:14 of kingspan a world leader in insulation products with a reputation for integrity yes
01:57:17 yes yes you say at the end of that section in
01:57:21 in in reference to their product literature would have been viewed not with unconditional acceptance but with a degree of trust and then we going on you say i have no doubt that in 2009 with the level of
01:57:32 doubt that in 2009 with the level of experience and knowledge i had i would have tended towards trusting what they were telling me in their literature after all their products had been researched and developed by people with extensive specialist expertise in the
01:57:44 extensive specialist expertise in the field
01:57:45 field and the company was viewed as being one with integrity it's fair to say is it that because of your own level and level of experience and knowledge in in
01:57:56 level of experience and knowledge in in 2009
01:57:58 2009 you would not have been in a position to challenge
01:58:01 challenge kingspan as to any of their assertions no i i would say that would be true i didn't have the specialist knowledge or experience that would be necessary to be
01:58:12 experience that would be necessary to be able to
01:58:13 able to to say hang on what you're saying doesn't sound right the same is true is it in relation to anything
01:58:19 anything asserted by the bba yes that would that would be right and and although you have said there that
01:58:29 that their assertions would not be viewed with unconditional acceptance would you agree that the overall effect of the project you undertook seems to be that you did in fact
01:58:41 seems to be that you did in fact unconditionally accept what you were being told both by kingspan and by the bba yes certainly the bba and to some extent the kingspan
01:58:52 the kingspan information as well uh not least because the key points appear to be supported by statements in the bba certificate indeed the two pieces of the two documents supported one another
01:59:04 documents supported one another did they not yeah yes they did yes all right i want to just look with you at some aspects of uh the evidence of some of the kingspan witnesses if we can go
01:59:16 witnesses if we can go please uh just briefly to the witness statement of philip heath which is kin3020709 and to page 60.
01:59:39 if we look at paragraph 8.20 please he says this
01:59:42 says this i cannot recall the labc system approval being issued as a draft by hereford however we would have checked the document in any event and we would have identified any errors or any
01:59:53 would have identified any errors or any points of interpretation of the building regulations with which we did not agree this did not mean that kingspan assumed any responsibility for the accuracy of the certificate
02:00:04 the certificate which remained an labc document we considered the labc and hcbcd which is hereford to be experts and that the certification
02:00:15 to be experts and that the certification would reflect their understanding and interpretation of the building regulations and approved document b so we can see there that where in a
02:00:26 so we can see there that where in a sense
02:00:26 sense you are saying that you relied on the specialist expertise and research and integrity of kingspan at the same moment kingspan say they were relying
02:00:37 were relying on your expertise do you see i do see yes i can see that mr heath says there that he he cannot recall um your system approval being
02:00:49 um your system approval being issued as a draft i think we know now that that was done and that you did send to andrew peck a draft of your certificate in summary would you have
02:01:00 certificate in summary would you have expected kingspan to pick up any inaccuracies or errors in that certificate and summary i would that was the expertise that they
02:01:11 i would that was the expertise that they were bringing to the exercise uh they knew the product they knew how it could be used i mean they as a as a company were advising the industry on how it should be used so that was expertise they had and i
02:01:23 that was expertise they had and i expected them to be honest and pick up any inaccuracies that's why i sent it to them not out of any naivety but at that time i just wouldn't have imagined that a company in kingspan's
02:01:34 company in kingspan's um position would want to risk the reputational uh damage from from knowingly marketing something
02:01:43 something with with the wrong information i see all right can we go now please to the witness statement of ivan meredith which is at kin3022312
02:01:56 is at kin3022312 and to page 42.
02:02:13 so it's kin three zeros two two three one two
02:02:20 thank you if we look uh please at paragraph
02:02:23 paragraph 92 d it's in about the middle of the page
02:02:28 page starting if you took no action why not and just to set it in context mr meredith was being asked there about this 2009 certificate
02:02:39 there about this 2009 certificate and why kingspan did not take any action in respect of its wording and technical content there he says this
02:02:47 says this we were paying experts to make opinions based on our product properties and their applicability in accordance with building regulations we supplied the product data they would write the guidance
02:02:59 write the guidance these bodies usually kept themselves in check
02:03:02 check and we were clutching at anything that would support the use of our products and very busy trying to balance all the needs of the company's business development therefore i believe it went unchecked
02:03:13 therefore i believe it went unchecked properly by us that being said the documents were very cheap
02:03:18 cheap compared to normal agrimon certificates that could cost twenty thousand pounds per year
02:03:23 per year compared to an initial two thousand pounds to produce the whole document focusing uh really there on the middle section
02:03:32 section were you aware at any stage of your involvement in this approval certificate that kingspan
02:03:39 kingspan were clutching at anything that would support the use of their products no i had no indication of that in any of our
02:03:47 our conversations or emails it was never even alluded to no were you aware that kingspan say
02:03:58 were you aware that kingspan say they were relying on your due diligence and expertise uh no i i don't believe that to be accurate because in in terms of my involvement it was very
02:04:09 in terms of my involvement it was very much a collaborative exercise that they they were providing expertise to the process uh they it wasn't all on on herefordshire or on labc no
02:04:22 on herefordshire or on labc no but but it was surely more on herefordshire and labc than kingspan who are after all the product manufacturer you and the labc are producing an approval certificate
02:04:33 approval certificate yes that that is true and and it was it was my belief at the time that that with with my work then going to labc for a further
02:04:41 a further uh check technical check that that there was a robust procedure in place to to counter that yes all right i mean the reality is
02:04:52 yes all right i mean the reality is putting it brutally i'm afraid is that no due diligence was carried out in respect of any of the assertions made in your type approval summary was it
02:05:03 it it doesn't appear to be the case or certainly there are some there are some matters there that should have been flagged up as concern that went yes all right can we
02:05:15 concern that went yes all right can we go back please to your first witness statement at page 40.
02:05:28 hbcs6029 thank you and if we look at your response please to question 68. i want to look in particular at the final paragraph there
02:05:40 final paragraph there where you say i think a point to make here
02:05:45 here is that there was sometimes a great deal of pressure to consider and accept innovative solutions for clients
02:05:52 clients which did not necessarily follow rigidly the approved documents private building control bodies were frequently known to exploit local authority going over please
02:06:14 stereotypes in their marketing go to the local authority and get tied up in red tape and rigid application of outdated approved document solutions come to us and we'll give you innovative
02:06:25 come to us and we'll give you innovative and free thinking approaches to compliance you then go on to say
02:06:31 to say this did lead to pressure on local authority surveyors to be open to new products
02:06:36 products and innovative solutions which the approved documents had yet to assimilate and approved documents did tend to be several steps behind industry development at any given time
02:06:49 industry development at any given time we then go on to say it was not uncommon for prospective clients to test our willingness to think outside the box before placing their business with us
02:07:00 before placing their business with us once you go down that road the next question is where you find the evidence
02:07:05 evidence to support these alternative approaches
02:07:09 i want to ask you about that because given what you have said thus far in your evidence about the nature of approved document b or the approved documents in general the
02:07:22 or the approved documents in general the training you had to think more widely and to think outside
02:07:27 outside of the approved documents and to come up with alternative routes or definitions was that in part because of this pressure that you've described
02:07:38 pressure that you've described here
02:07:41 here i'm sorry could could you repeat the question but of course i'm so sorry i don't think i put it very well or it's far too long you told us earlier that when you were coming to formula judgment that k-15 was
02:07:53 coming to formula judgment that k-15 was a material of limited combustibility you decided in part as a result of your training
02:07:59 training to step outside of the strict definitions within approved document b and to come up with an alternative yes yes and all i'm asking
02:08:11 alternative yes yes and all i'm asking is whether that was in part related to this pressure that you've described in the section of your witness statement i've just read to you
02:08:22 i've just read to you uh yes it was now i think the important thing
02:08:26 thing difference to to point out is this is this is a
02:08:30 this is a a principle applied in our building control business as when we were dealing with building control clients which was our our bread and butter if you like that's what we did so as far as this this sort of limited
02:08:42 so as far as this this sort of limited exercise with kingsman goes there was no incentive for me to try and
02:08:47 try and you know please kingspan or or keep them happy in terms of future business because there was no future business kingspan were not clients of ours but i felt when i was writing the statement that perhaps it was important to point this out
02:08:58 to point this out as the backdrop against we were which we worked
02:09:01 worked and it perhaps might explain why when dealing with the kingspan exercise my the way i went about it might have been influenced by the way i
02:09:13 might have been influenced by the way i went about our normal building control activity i see so more broadly because of the pressures you've described here to think outside the box and come up with innovative solutions
02:09:25 and come up with innovative solutions that had become a way of working which may have affected the way in which you approach this assessment is that it that's right even though that incentive wouldn't have been there for kingspan
02:09:36 wouldn't have been there for kingspan it wouldn't have mattered to us whether we kept kingspan happy or not if i'm honest because we weren't going to get repeat business it wasn't it wasn't part of what we did but but i'm sure
02:09:45 i'm sure that's the way we worked and and that would have come out in the way i approached this exercise why do you say there was no incentive for hereford and you weren't going to get repeat business
02:09:58 well i mean these type approvals certainly that well the kingspan ones were the only ones we dealt with uh but they came along once in the blue moon and the the the payment was
02:10:11 and the the the payment was inconsequential really 500 pounds is about what we would have charged for the building control on a kitchen extension so it was
02:10:17 so it was in terms of our income it was neither here nor there it was it was inconsequential so really there was there was no incentive
02:10:28 really there was there was no incentive for us to to do these type approvals other than a sort of obligation to help labc when they asked us to um and there was certainly no incentive
02:10:39 um and there was certainly no incentive to to be overly generous in to kingspan not deliberately because you know this wasn't a source of income this wasn't an income stream for us there was
02:10:49 there was they were small sums of money once in a blue moon
02:10:52 blue moon usually at a time when we were busy enough anyway and would rather not have the extra workload all right i want to take you back please to the uh service manual we looked at earlier if
02:11:04 service manual we looked at earlier if we can go back to that it's eight hbc 6049 and if we can go i think to page 16
02:11:23 yes if we look please at section 3.2 assessment checking level of service we can see this in the opening paragraph it is vital for the type approval service
02:11:35 the type approval service that a high level of assessment is applied in order to secure user confidence service credibility and to avoid repetitive faults due to an
02:11:46 and to avoid repetitive faults due to an initial
02:11:47 initial oversight accordingly all type approval projects
02:11:51 projects should be comprehensively checked in all respects
02:11:55 respects singular reliance upon a risk-assessed acceptance or other form of exclusions from full checking
02:12:03 checking or reliance upon previous examples should only form a limited controlled and recorded part of any assessment process do you see that
02:12:14 that yes do you know whether or not you read that
02:12:17 that at the time you were carrying out your assessment i don't know i i was certainly aware of this second level of checking labc committed to um and my recollection is
02:12:30 committed to um and my recollection is that this was discussed in the telephone conversation but as with the discussion about the bba certificates i i i can't recall whether whether i'd read this
02:12:40 read this section or whether it was just given to me verbally or both but i was certainly aware of it yes so i know that this section goes on to discuss a second
02:12:51 discuss a second check and and what is required in in respect of a second check do you consider that the first paragraph of this section that i've just read to you
02:13:00 you is directed not to you the author of the certificate in summary but to labc
02:13:08 i i believe it to be yes because when we look at the bullet points which which define the uh the type of checking that might be carried out that would have been labc um
02:13:20 that would have been labc um activity not not heritage council i see and what about the section towards the end of the first paragraph that i've just read to you which says that they should be
02:13:31 which says that they should be comprehensively checked in all respects
02:13:35 and then goes on to say that singular reliance
02:13:39 reliance upon previous examples should only form a limited
02:13:43 a limited controlled and recorded part of any assessment process if we think about that it's fair i think for me to say that
02:13:53 that your type approval summary relied entirely
02:13:57 entirely on previous assertions which went unchecked by you is that fair yes in in respect of the bba certificate yes
02:14:08 in respect of the bba certificate yes yes
02:14:11 but you consider that that paragraph and the advice in it as to the level of quality was not directed to you and not for you to consider is that it i
02:14:22 and not for you to consider is that it i i
02:14:22 i read it to be a a sort of a robustness to the process that meant that no one local authority could issue a document
02:14:31 document without it being verified by other means you know to stop inaccurate information circulating in the wider industry
02:14:44 industry i see do you consider that the work you carried out was of an adequate standard mr jones
02:14:56 was of an adequate standard mr jones um i i think in terms of the scope of what i did it it matched what um what labc had asked of us but
02:15:07 asked of us but with hindsight i don't believe that that scope was adequate i i don't i don't believe it should have been done
02:15:14 been done uh to that sort of level i see and we've we've obviously looked at some of the work i did and and appreciate that because of my lack of experience
02:15:26 of experience some of it was not it was not what uh what should have been written so in terms of
02:15:33 terms of given what you have said about the scope of the project as it was set out for you what you're saying is that you did follow that and you did carry out that work adequately within the parameters of that
02:15:45 adequately within the parameters of that scope but the scope itself essentially broke this from the start is that fair
02:15:52 that fair i believe so i i when i when i look back at the scope that was asked of us you know 500 pounds worth of work i don't believe it was appropriate the the result of that sort of scope
02:16:04 the the result of that sort of scope in terms of the certificate was always going to be very very limited and barely scratched the surface and i can see now with hindsight that when you work to a very limited
02:16:15 that when you work to a very limited scope like that there's a high risk that you don't dig down into the into the real meat of it um in which case then it begs the question
02:16:26 begs the question should it be done at all as you either do it fully or not at all can we just go down please to section 3.5
02:16:35 3.5 i think it's on page 18.
02:16:42 this is about resources and competency labc hq and local authorities shall deploy sufficient experience and qualified staff to type approval
02:16:53 qualified staff to type approval projects
02:16:54 projects in order that every application is given a high level of professional assessment and decision making and and so on and then there are three bullet points um above which the manual states if a
02:17:06 um above which the manual states if a local authority is faced with resource or logistical problems in respect of any particular project or proposal it should either seek to pass the project to another authority
02:17:16 authority refer the matter to the technical coordinator or set up a joint working arrangement as far as you are aware was any consideration given
02:17:27 consideration given at any stage given your acknowledged lack of
02:17:31 lack of experience to passing it to another authority
02:17:35 authority or setting up a joint working arrangement or looking for any kind of formal help i think the consideration was that that initial um an initial discussion between myself
02:17:47 um an initial discussion between myself and chris jenner and between myself and labc where i was considering declining doing the work uh not just for me but powerful council
02:17:57 council and say actually i don't think we have that expertise and that would be in line with
02:18:01 with with you know what this section of the document is saying actually do we have the expertise but it was actually that conversation with labc where the very limited scope was discussed yes where we concluded that
02:18:14 discussed yes where we concluded that oh okay yes for that sort of scope uh yes perhaps we do have the resources and the competency to go as far as that scope needs us to go and and
02:18:25 go and and perhaps you know in in a different world had all parties to that process being honest and open then then the result would have been very different potentially but that i i think we did give consideration
02:18:37 that i i think we did give consideration to it
02:18:38 to it and it was the and it was the scope given to us by labc that uh that allowed us to go forward all right um referring back to what you
02:18:49 all right um referring back to what you said there about had all parties been honest and open can i ask you this do you consider that you were misled during this process yes i do
02:19:00 during this process yes i do by whom
02:19:03 i i would say by uh kingspan and by the bba although i don't know to what extent kingspan influenced the content of the bba certificate
02:19:14 bba certificate you know with knowing now what was going on
02:19:17 on but by both those documents there were some very misleading statements very misleading diagrams that seem to me now to be designed quite deliberately to lead
02:19:28 designed quite deliberately to lead people down a certain a certain interpretation you know it would have been so easy to include
02:19:35 include clarifications and caveats about what the testing actually related to what the what the limitations on the use of the product in systems over 18 meters
02:19:46 of the product in systems over 18 meters where it would have been very very easy to do both in the kings fan literature and in the bba certificate and it seems to me odd
02:19:53 to me odd that there's almost a deliberate move not to include those clarifications and allow
02:19:59 allow different interpretations by ordinary industry professionals like me not not specialists but just industry professionals yes yes thank you you've spoken a little
02:20:12 yes thank you you've spoken a little about the checks that you understood would be carried out at the labc when you had finished your part in this assessment but i think we can go to it if we need
02:20:23 but i think we can go to it if we need to
02:20:24 to i think in your first witness statement you actually say that you're you were not sure in 2009 what arrangements were in place or what those checks would comprise is that right
02:20:37 would comprise is that right that's right i i knew there was a checking procedure and it's and it's possible and likely that i saw that section of the manual but of course that lists out quite a number of different options for checking so i i didn't know
02:20:49 options for checking so i i didn't know which of those labc would choose to use they they had access to every local authority building control department in the country including the urban ones where high-rise buildings
02:21:01 the urban ones where high-rise buildings are the norm they had access to technical consultants because
02:21:06 because labc were marketing i think some technical consultancy services in the wider industry so they had various options to that they could have used to take my report and and
02:21:17 report and and and get it checked but i didn't know what they proposed to do i just knew they were going to do some level of challenge yes all right and
02:21:24 and you said to us earlier that that knowledge provided you that knowledge was significant to you and it provided you uh with some comfort when you carried
02:21:35 uh with some comfort when you carried out your work did you consider no first did you flag up to anyone at the labc that you were relying on
02:21:46 were relying on them to check very thoroughly the work you had been done or that you were expecting comments or that you were concerned in any way i i believe i did in that
02:21:57 in any way i i believe i did in that initial
02:21:58 initial telephone conversation i see there was an exchange where where you know i went from actually i don't think we can do this to oh okay if what you're saying is true
02:22:09 to oh okay if what you're saying is true about the scope and about the checking procedure then maybe i can and i think that in itself was an indication that the knowledge of the checking procedure was one was a key factor for us saying yes okay we'll do it yes but you
02:22:22 saying yes okay we'll do it yes but you had no way of knowing did you i mean i know it's difficult because we don't know who it was that you spoke to initially
02:22:27 initially initially at the labc but you had no way of knowing whether that person would have any involvement at all in the final checks so i suppose what i'm asking is did you consider at a later stage perhaps when
02:22:40 consider at a later stage perhaps when you sent in your draft document flagging up to the labc again that you you didn't in fact have any experience or knowledge of these areas and that you were relying on them to
02:22:51 and that you were relying on them to check what you had done did you consider doing that no i didn't think i did i think i trusted otc to to do what we discussed i think i was aware that herefordshire council was it was a known quantity to them in
02:23:03 was it was a known quantity to them in terms of you know the type of type of work and expertise we had and and
02:23:08 and and i just i knew that once i submitted the report to labc there was another process to go through it was all in the manual and the process flow chart so i think i trusted that they would do what
02:23:20 think i trusted that they would do what was necessary um but i didn't pursue that with them again i wish i had if i'm honest um but no i didn't
02:23:31 if i'm honest um but no i didn't all right i want to look with you very briefly um at another certificate for k-15 issued by the labc in 2013 and by that
02:23:42 issued by the labc in 2013 and by that time it was called a registered detail certificate and i think you did have some involvement in it if we can go to the certificate please it's a kin
02:23:58 409546
02:24:09 yes so this is the certificate itself and we can see on the left hand side of the page that the date of issue is the 28th of august 2013. yes yes and that statement sorry and that
02:24:22 yes and that statement sorry and that statement
02:24:23 statement is signed off by barry turner on behalf of the labc if we go on please to the drawings and document list which came with this certificate
02:24:34 came with this certificate that is at kin409547
02:24:46 yes you tell us in your first witness statement i don't think we need to go to it but if you need to we can do that this assessment
02:24:57 we can do that this assessment this renewed certificate the assessment was undertaken by colin davis at hereford building control is that right that's right yes and i think at that
02:25:08 that's right yes and i think at that time you were his line manager were you yes
02:25:16 do you know how this assessment came to be the responsibility of mr davis rather than
02:25:22 than rather than you was it just because of your respective positions at the time yes it's because i was as the manager of the department i was doing far less technical assessment work uh at that time but colin was a fully
02:25:36 uh at that time but colin was a fully practicing very competent building control officer or senior voter control officer so i i discussed with him in taking the renewal
02:25:47 in taking the renewal yes all right and did you review any part of this work before it went back to the labc
02:25:55 did you i think i did i i believe colin brought it back to me he knew of my previous involvement so i think he after he'd done his work i think i i i talked it through with him before he did his assessment
02:26:06 his assessment and probably did a review with him afterwards um of what what his findings were can we just scroll down in this
02:26:17 can we just scroll down in this in this drawings and document list please
02:26:24 perhaps to the to the next page
02:26:28 yes and we see that it takes quite a different form than than the one that you prepared doesn't it
02:26:37 it yes yeah what i can tell you we can go through it if we need to but what i can tell you is that this renewed certificate does not contain the words
02:26:47 words k15 can be considered to be or can be considered a material of limited combustibility anywhere and all i wanted to ask you was whether you know why
02:26:59 whether you know why that particular wording was removed for this issue of the registered detail certificate um i think the the document i
02:27:11 um i think the the document i created in 2008 2009 yes there was a version of that created for this renewal by colin he in fact took took the
02:27:22 by colin he in fact took took the original document and and amended it um and and the wording remains in in that document so it wasn't it wasn't removed it just doesn't appear in in the part we're looking at now um in
02:27:34 in the part we're looking at now um in fact
02:27:35 fact the part we're looking at now was was wording that was put forward by kingspan um was in fact this was suggested word for word by gareth mills of king spen wasn't it
02:27:46 of king spen wasn't it yes it was yes all right but you say do you that there's another part of this document which you think does contain the words material of limited combustibility yes as i say it's the original document
02:27:58 yes as i say it's the original document that i wrote in 2008 amended by colin davis i see and do you think that change was made at the labc
02:28:10 uh which change the addition of this appendix was added by labc but in consultation
02:28:22 by labc but in consultation with myself and colleen i see all right we might come back to that if we need to i just want to look now please at um some email correspondence from a little later in 2013.
02:28:34 later in 2013. if we can go please to labc 305351
02:28:51 if we can go down please to page three which is the bottom of that email chain
02:28:59 yes if we can
02:29:02 zoom in on on the last email chain there that is an email chain from david ewing of the labc to you date of the 19th of december 2013. do you see that
02:29:14 you see that yes yeah and i would like to take you to the section it's a bit dense i'm afraid but if you go after hi dave if you go one two three four five lines down to the section
02:29:27 four five lines down to the section starting i have also been approached do you see that yes yeah he says to you there i have also been approached by celetex who have queried our interpretation of
02:29:39 who have queried our interpretation of adb
02:29:40 adb in relation to the k-15 product i have no technical data behind our archive system so can't dig into it essentially the query is in relation to use of a
02:29:51 use of a pur board in a position requiring fire resistance particularly if it is used over 18 meters adb 4 12.5 to 12.7 and definition of
02:30:03 adb 4 12.5 to 12.7 and definition of limited combustibility wondered if there was any testing undertaken to demonstrate the external boarding protected the internal core of the board
02:30:13 the board or any background on the research process undertaken i appreciate this may have been some time ago as i think it was originally a lantech certificate i think that's a little bit confused in
02:30:25 i think that's a little bit confused in terms of its wording but would you agree with me that essentially what mr ewing is saying there is that celetex
02:30:32 celetex are questioning the the terms of the original certificate from 2009 in relation to limited combustibility it does seem to be heritated yes yes all
02:30:44 it does seem to be heritated yes yes all right
02:30:44 right so can we go up please to your reply which comes the next day so if we scroll up
02:30:55 uh i'm afraid and up again i think your email is quite a long one and again sorry so page one
02:31:09 you say there hi david i'm not sure what specific issues have been raised by celetex but below are some extracts relevant to the fire performance and testing of k15
02:31:22 performance and testing of k15 firstly from the bba certificate and then you have copied and pasted section 7
02:31:29 section 7 behavior in relation to fire from the bba certificate into your email yes yes all right let's scroll down please
02:31:40 to the next section of this page
02:31:55 and then at the very bottom in the smaller blue writing i think this is you again you say followed by an extract from kingspan's own technical literature and so now if we go over to page two
02:32:08 please that is it's quite difficult to see but that is the section we looked at earlier isn't it from kingspan's marketing literature yes containing the phrase at the end of
02:32:21 yes containing the phrase at the end of it and is therefore acceptable for use um above 18 meters yes yes yes and then just below that there's in blue this is you again
02:32:32 this is you again and these from our internal assessment and if if we can scroll down again please
02:32:44 here you have copied and pasted sections from the type approval summary the relevant sections requirement b and b4 external fire spread yes yes so scrolling down
02:32:57 yes so scrolling down a little more please to the bottom of that page
02:33:01 that page you say at the bottom there in blue essentially as the board is described as class naught it can be termed a material of limited combustibility and so in terms of the relevant part of
02:33:13 and so in terms of the relevant part of doc b
02:33:14 doc b it is suitable for use within the wall construction even at heights over 18 meters do you remember writing that mr jones
02:33:26 i i don't remember writing that and that seems to be a real simplification i mean i've sent i've sent all the backgrounds to the to the judgments but i haven't
02:33:37 the judgments but i haven't it's a very simplistic way of writing i can't i can't recall that i'm not sure it's a simplification it's it's inaccurate isn't it yes yes and the reason i wanted to ask
02:33:49 yes yes and the reason i wanted to ask you about this is because in your evidence earlier you seem to be very clear that many years before this in 2009 you were very clear as to the difference
02:34:01 you were very clear as to the difference between class naught and limited combustibility and how those
02:34:06 how those things uh related to one another in fact she went so far as to say that you describe the confusion in industry about that matter
02:34:17 about that matter confirmed that you had no confusion in your mind on that issue and in fact i think you said that you were required to understand it well enough to
02:34:26 enough to correct the misunderstandings of others is that right yes and i still believe that to be the case yes yes so how did you come in 2013 at the end of 2013
02:34:38 end of 2013 to be saying in response to a request from the labc for an explanation as to how your type approval
02:34:47 approval certificate said what it said how do you come to be saying this to david ewing of the labc can you explain that i can't explain
02:34:59 can you explain that i can't explain that other than it's it's wrong do you think it might be the case mr jones that you were not quite so clear in your own mind
02:35:10 own mind in 2009 or even in 2013 as to what class naught and or limited combustibility might have meant i believe that i
02:35:23 might have meant i believe that i was clear on it it was it was it was quite a fundamental requirement i don't
02:35:30 don't i don't think for me there was there was a sort of ambiguity that that sentence suggests no but that sentence is equally that sentence is very clear
02:35:41 equally that sentence is very clear do you have any idea how you can have come to write that it's just an aberration is it it it is i i can only say it it has been so long since i'd since i don't have any detailed involvement in this but but
02:35:54 involvement in this but but i i've written a very simplistic account of
02:35:59 of of how i arrived at the conclusions well again forgive me but it's not simplistic it's us it's just wrong isn't it it is wrong yes yes all right do you know whether david
02:36:12 yes all right do you know whether david ewing went back to celetex with that explanation did you hear any more about it
02:36:17 it i don't believe i did no right other than this and this series of emails
02:36:24 emails were you at any stage made aware of any concerns or complaints from any individual or organization in relation
02:36:34 relation either to the 2009 certificate for k-15 or to the 2013 certificate for k-15 i i can't recall being made aware of any
02:36:46 i i can't recall being made aware of any no all right but mr jones at this stage i can tell you that i've come to the end of my prepared
02:36:54 prepared questions for you but i'll um hand back over to the chairman because we need now to take another short pause yes thank you very much well mr jones at
02:37:05 yes thank you very much well mr jones at this stage we have a short break so council can check that there aren't any questions that she's omitted to ask and also to allow other people following the inquiry to suggest
02:37:16 following the inquiry to suggest possible further questions so we'll have a break until half past four and at that point we'll find out whether there are any more questions for you all right right and usual instruction
02:37:28 all right right and usual instruction don't talk to anyone about your evidence please
02:37:31 please during the break right so you would have passed for them thank you
02:55:45 welcome back everyone now see if there are any further questions for mr jones mr jones just to check up can you see me and hear me clearly yes i can very good um we'll now see
02:55:57 yes i can very good um we'll now see whether
02:55:58 whether uh miss troop does have any further questions for you miss troop yes just one further question
02:56:07 and uh it's this we've been through a great deal of evidence in just one day and we've discussed a number of issues and i want to ask you this looking back
02:56:18 and i want to ask you this looking back over all of that is there anything that you would have done differently
02:56:25 i from from where i understand the thing i would have done differently was was go with my first instinct right at the very start and say i don't believe we're equipped to do this exercise yes
02:56:36 exercise yes all right thank you thank you well mr jones
02:56:41 jones um it's right that i should thank you on behalf of not only myself but the whole panel for making yourself available today to give us your evidence um i'd like you to know that it's been extremely valuable to us to hear what
02:56:52 extremely valuable to us to hear what you have to tell us so we're very grateful to you for coming along to do that
02:56:57 that and uh that is all the questions we have for you
02:57:00 for you and so you'll know as it were free to go about your business thank you very much indeed thank you and that's the end of the hearing for today we will resume
02:57:12 today we will resume at 10 o'clock on monday with another
02:57:20 witness
02:57:23 you