Local Authority Building Control (LABC) - Wednesday 8th December 2021 (1/2)

8 December 2021 · Barry Turner (LABC), Kate Grange QC (Counsel to the Inquiry) · 2:56:51
▶ Watch on YouTube Open in interactive viewer

Evidence from Barry Turner, former Director of Technical Policy at LABC, examining the certification process for Kingspan K15 insulation and the type approval system.

Key moments

Full transcript

# Transcribed with OpenAI Whisper (medium model)

# Source: Local audio transcription (no YouTube captions available)

00:00:30 Good morning, everyone. Welcome to today's hearing. Today we're going to begin hearing

00:00:36 evidence from witnesses representing some of the organisations about whom we heard from

00:00:43 the Council making opening statements in the last two days. Yes, Ms Grange.

00:00:49 Yes, Mr Chairman. Could we have Mr Barry Turner, who is our first LABC witness, please?

00:00:55 Yes, thank you very much.

00:01:04 Good morning, Mr Turner.

00:01:05 Morning.

00:01:06 I understand you're going to make the affirmation.

00:01:09 Yes.

00:01:10 Thank you very much. Would you then please read the words on the screen?

00:01:13 I do solemnly, sincerely and truly declare and I affirm that the evidence I shall give shall

00:01:19 be the truth, the whole truth and nothing but the truth.

00:01:22 Thank you very much indeed. Would you like to sit down please and make yourself comfortable?

00:01:26 There's some water there if you would like it.

00:01:49 Good. All right.

00:01:50 Okay.

00:01:51 Good. Yes, Ms Grange.

00:01:53 Yes, good morning, Mr Turner. Can I start by thanking you very much for attending this

00:01:58 public inquiry today to give your evidence. It is very much appreciated. If you have any

00:02:04 difficulty understanding any of the questions I'm going to ask you, please don't hesitate

00:02:09 to ask me to repeat the question or put the point in a different way. And can you try

00:02:13 and keep your voice up because there's a transcriber sitting to your right who's taking a note,

00:02:19 a clear note of your oral evidence. Now you provided two witness statements to the inquiry.

00:02:26 The first one was dated the 14th of February 2020. And the second statement, which was

00:02:32 a statement which amended your original statement and encompassed all of your evidence, was

00:02:37 dated the 9th of October 2020. If we can pull that up, that's at LABC 0011202.

00:02:50 So there's your second amended statement. And if we look at page 47, is that your signature?

00:02:59 It is.

00:03:00 Yes. And we can see it's dated the 9th of October 2020. And have you read that witness

00:03:06 statement recently?

00:03:08 No.

00:03:09 Okay. Well, I'll take you back to certain passages during your evidence. Can you confirm

00:03:15 that the contents are true and accurate?

00:03:18 They were, I believe so at the time. Yes.

00:03:21 Okay. Thank you very much. And you've also helpfully provided a document for the transcript.

00:03:27 That's at LABC 0011205, which sets out the amendments that you made to that second corrected

00:03:34 statement. Have you discussed the evidence you're going to give with anybody before coming

00:03:40 here this morning?

00:03:44 Legal representatives, yes.

00:03:46 That's fine. Okay. But nobody else?

00:03:48 No.

00:03:49 Thank you. Now, just to start with, I'm going to ask you some questions about your background.

00:03:53 And if we can pull up paragraph 12 of your statement at page three. You tell us there

00:04:05 in paragraph 12 that you are a chartered building control surveyor and a member of the Royal

00:04:10 Institute of Chartered Surveyers with over 53 years experience in surveying and building

00:04:16 control. Is that correct?

00:04:18 It is.

00:04:19 Thank you. And you tell us on the first paragraph of the statement on page one that at the time

00:04:27 you made your statement, you were employed by the District Surveyor's Association as

00:04:32 director of technical policy. And you explain that the District Surveyor's Association operates

00:04:38 under the trading name, Local Authority Building Control, and is commonly known by that name,

00:04:44 usually abbreviated to LABC. Is that correct?

00:04:48 Thank you. And you tell us there that you were the director of technical policy. Are

00:04:59 you still employed by the LABC in that role?

00:05:02 No.

00:05:03 Is it right that you retired from employment?

00:05:06 Yes.

00:05:07 When did you retire?

00:05:09 March of this year.

00:05:11 Thank you. Now, if we go to page four of your statement and look at paragraph 14, you tell

00:05:18 us that you joined the LABC in October 2006 as director of technical policy. Is that correct?

00:05:28 I'm not sure the job title is correct. I can't tell you what it was, to be perfectly honest,

00:05:34 but it was a similar role. Yes.

00:05:37 And was it a senior technical role within the LABC?

00:05:40 Yes.

00:05:42 Now, I'll ask you some more questions about that role in a minute, but just briefly, because

00:05:47 we don't get this from your statement, just tell us what jobs, what employment had you

00:05:51 been involved in before that time?

00:05:55 Principally Local Authority Building Control from trainee to manager of the service throughout

00:06:01 my career.

00:06:04 And had you stayed within a particular area doing Local Authority Building Control work?

00:06:08 Yes, in the North Wales area.

00:06:11 Yes, thank you.

00:06:13 Did you move between local authorities in the course of your career progression?

00:06:19 I did. Usually as a result of local authority reorganisation. We suffered two local authority

00:06:27 reorganisations during my time at employment.

00:06:32 Yes, thank you.

00:06:33 And staying with paragraph 14 there on page 4, you continue to say that you were appointed

00:06:41 to represent the LABC and Local Authority Building Control on government-initiated working

00:06:46 groups together with various technical committees and other industry advisory forums. Is that

00:06:52 correct?

00:06:53 Yes.

00:06:54 Yes, and we'll come to some of that work in due course. Paragraph 15, below that, you

00:07:01 say that your responsibilities include keeping members informed of legislative changes and

00:07:07 we're able to do so to offer advice on the application and interpretation of building

00:07:12 control legislation and regulations to local authorities throughout England and Wales and

00:07:18 also to collate and disseminate information. Is that right?

00:07:23 Yes.

00:07:25 And then we understand from Mr Bassan's statement that you were his line manager, is that correct?

00:07:33 Yes.

00:07:34 He, between February 2011 and May 2015, he was the head of technical practice and communications

00:07:40 at the LABC. Is that right?

00:07:44 He was a colleague, yes.

00:07:45 Yes. And you were his line manager?

00:07:48 I think that's probably the correct interpretation, yes.

00:07:53 Did you manage anybody else in your role as director of technical policy or whatever title

00:07:59 that role had?

00:08:00 No.

00:08:01 No.

00:08:02 No. It was a singular role, in effect.

00:08:06 Yes. Now, you said that you weren't entirely sure about the title of your role. Can we

00:08:12 just look at an email relevant to this? It's LABC 302825, page 101. This is an email dated

00:08:28 the 20th of November 2006, so it must have been shortly after you began working at the

00:08:35 LABC. And we can see that you're telling somebody called Nila Dionerine in the second paragraph,

00:08:48 you say, as for title, anything as long as it is polite. My official employment title

00:08:53 is technical coordinator, but it was felt that while this was very specific and correct

00:08:58 as far as dealing with our members are concerned, in some instances, this may not portray the

00:09:02 correct image to the outside world. Who am I to argue? Paul has suggested something along

00:09:08 the lines of director of technical services, which is fine by me. The board don't want

00:09:13 a technical director because it implies membership of the board. Do you see that?

00:09:17 Yes.

00:09:18 And then you say, go for director of technical services, but don't print too many copies.

00:09:22 Yeah.

00:09:24 Does that help you in terms of what title you came upon in terms of your role?

00:09:32 Yes. I think it also describes what the role involved.

00:09:36 Yeah. And can you just explain to us why the role of technical coordinator

00:09:41 didn't portray the right image to the outside world? What was the problem with that title?

00:09:45 This was a discussion that I'd had with the chief executive at the time. The idea was that I would

00:10:01 represent the membership and they wanted something that portrayed a

00:10:16 level of responsibility within the organisation. I think that's the best way I can describe it.

00:10:23 Yes, that's helpful. Thank you. There are references in, for example, the LABC type

00:10:30 approval service manual. So in some of the manuals you were using, there are references to the role

00:10:36 of technical coordinator. Were you different from that? Was your role distinct and different

00:10:43 from the technical coordinator role? Did somebody else perform that role?

00:10:51 Yes. I think that was primarily an administrative position.

00:10:58 Right. So where we see references in the manuals to technical coordinator,

00:11:04 and thinking back, for example, to the period, say 2006 to 2012,

00:11:09 are you saying that wouldn't have been you? No.

00:11:12 No. Okay. Can you help us as to who that would have been, the technical coordinator at that time?

00:11:17 It would have been one of the administrative assistants within the office. It was a role of

00:11:26 that nature. So are you saying- It was not a technical person. It was an

00:11:34 administrative person. Right. I see. So emphasis on the coordinator

00:11:39 rather than the technical. Yes.

00:11:41 I see. Thank you. Now, we don't need to go to this, but Lorna Stimpson has said in her evidence

00:11:50 that until Mr. Basson's appointment in 2011, you were the only person at the LABC

00:11:57 with technical expertise. Is that right? Probably correct, yes.

00:12:03 Yes. And she also says that the technical input and any technical decision-making

00:12:10 for the registered details scheme was the responsibility of the director of technical

00:12:14 policy as the most senior technical member of staff, i.e. that was your responsibility.

00:12:21 Do you agree with that? Not entirely, no.

00:12:25 Can you explain why? It was a function

00:12:30 carried out by the membership. If there was a

00:12:41 problem, then it could well be referred to me, but there was also a-

00:12:53 I don't know whether it was a working group or a committee, but basically a membership group

00:13:00 that it would be referred to for a peer review.

00:13:05 Right. So it wasn't entirely, you know,

00:13:10 on my say so. I see. Yes. Thank you.

00:13:14 Now, in terms of any training you received, and particularly training relating to the building

00:13:20 regulations and associated guidance, which you've said you were involved with, in your role as

00:13:27 director of technical policy, and given the responsibilities that you've described,

00:13:31 would it be fair to assume that you were required to know and understand the building regulations

00:13:36 and the associated practical guidance, including in the approved documents? Yes.

00:13:42 Do you have any qualifications which are relevant to the interpretation of the building regulations

00:13:49 and the practical guidance associated with it? Yes. At the time I was doing such training,

00:14:03 there was an organisation, in fact, it was the Institute of Engineers, or it was an engineering

00:14:18 institute associated with local authorities. They had a building control faculty and they had

00:14:29 examinations for building inspectors, they were called at the time, not building control officers,

00:14:38 and I took those examinations and followed up with various CPD issues and eventually with the

00:14:47 RICS. Right, yes. So when did you take that qualification that you've just described?

00:14:53 Well, with the RICS it was because of my qualifications at the time.

00:15:04 The Institute of Building Control had

00:15:19 a two-stage examination process of which I had completed the higher stage, and because of that,

00:15:27 because of experience and time, was accepted into the RICS for charter membership.

00:15:40 Right, and can you just give us some dates? When did you do that

00:15:43 Institution of Building Control qualification? I've got no clue.

00:15:48 Was that right at the beginning of your career? It would be

00:15:51 the late 70s, early 80s. Yeah. And when were you accepted into the RICS?

00:16:03 Whenever the Institute of Building Control was accepted into the RICS,

00:16:07 and I'm sure there are records that will tell you that. Okay, thank you.

00:16:11 Now you've mentioned CPD there, can you think back between 2006 and 2015,

00:16:18 did you attend any specific training relating to the building regulations and the associated guidance?

00:16:25 No, I think it was the other way around. I was the one providing it from knowledge gained

00:16:33 with my involvement with the government working groups. Yeah. The build up to the

00:16:40 introduction of changes to the legislation, and so it would be, my CPD was self-inflicted.

00:16:53 I see, you were the trainer. Yes.

00:16:56 Yes, I see. And would you say during that period, 2006 to 2015, that you were familiar with approved

00:17:02 document B, the practical guidance on fire safety? I would like to think so, yes.

00:17:07 Yes. Yeah. Would you regularly read approved document B? Would you go back to it during the course of your work?

00:17:15 No, not unless it was necessary, or if I was asked a, the role that I carried out was such that it was

00:17:29 reactive rather than proactive, so if I was asked a question then I would research the answer.

00:17:35 Right. So each time there was a new version of approved document B, for example 2006, 2010,

00:17:41 2013, would you take time to go and look at that version? Yes.

00:17:50 Had you delivered or attended in any way any form of training relating to the requirements

00:17:57 within the building regulations and approved document B about the use of external wall

00:18:01 materials in buildings over 18 metres in height? Not specifically, no.

00:18:06 No. So let's take 2009 for example, how good would your understanding have been

00:18:17 at that time, 2009, about the requirements for external wall arrangements in buildings

00:18:23 over 18 metres in terms of fire safety?

00:18:35 I would have researched it had I been asked a question about it. I wouldn't have carried out

00:18:48 such research without purpose. I see, yeah. If someone had asked you in 2009 what the meaning

00:18:56 of the phrase limited combustibility was, would you have known or would you have had to go and...

00:19:01 I would have known where to look for it. Right, yeah. Did you have any understanding

00:19:07 about the significance of that phrase in terms of building materials and their use over 18 metres

00:19:13 in 2009? I think that is a difficult question to answer because my understanding now is far

00:19:23 greater I would think than it was in 2009, so I can't say what my knowledge was in 2009.

00:19:30 Yes, but do you remember a time when your knowledge and awareness changed in relation to the use of

00:19:36 materials over 18 metres?

00:19:43 Again, I think the memory of that is clouded by events which have happened since.

00:19:53 Yes, I understand. What about your understanding, thinking back to say around 2009, of the BR135

00:20:01 guidance and BS8414 large-scale testing, did you have any familiarity with that aspect of

00:20:09 approved document B and then those particular guidance documents? I knew that they were

00:20:15 referenced in ADB. I didn't know the content of those documents in any particular detail.

00:20:22 Yeah. Did you ever read BR135 on external wall materials? Probably.

00:20:30 Probably. Now, just some more questions about LABC as an organisation now.

00:20:40 And if we look at paragraph 13 of your statement at the bottom of page 3, you tell us this. You say

00:20:47 LABC is a small, currently around 30 employees, a not-for-profit company established with support

00:20:54 from the local government associations. It was set up following the introduction of private sector

00:21:00 competition into building control and the creation of approved inspectors. Prior to that time,

00:21:07 building control was a regulated activity within the sole remit of duly authorised building control

00:21:12 departments of local authorities. And then I want to pick it up again in paragraph 17 on page 4.

00:21:21 You say there specifically LABC supports local authorities, LABC members, in achieving ISO

00:21:31 accredited standards within which to work, conduct learning, guidance, qualification programmes,

00:21:37 and promotes technical consistency in the application of building regulations. Currently,

00:21:43 all local authorities across England and Wales are members of LABC, but this is on a completely

00:21:48 voluntary basis. LABC has no formal regulatory status. Now, just with reference to what you say

00:21:53 in that paragraph, can you just in general terms explain how the LABC would go about

00:21:58 promoting technical consistency in the application of building regulations? What methods would it

00:22:04 deploy to try to do that? Newsletters, guidance notes,

00:22:13 general information sheets within membership, and it was not all necessarily generated

00:22:23 at LABC headquarters. And can you tell us why was technical consistency an important goal for the

00:22:32 LABC? One of the criticisms levelled at local authority building control, because I think at

00:22:38 the time there were some 350 local authorities, it's down to around about the 300 mark now.

00:22:46 You therefore have 350 different surveillance systems, and you have to be able to do that.

00:22:56 You therefore have 350 different surveying departments trying to interpret guidance.

00:23:07 One of the criticisms levelled was that it was not consistent because of the

00:23:18 the way that the documents were approached, as also some members had greater knowledge than others,

00:23:26 and it was useful to use that by way of educating those members that were sort of, shall we say,

00:23:36 less in contact. So it was about trying to get everybody to have a similar approach

00:23:46 rather than working in isolated cells. Yes, and was it considered that you needed to have that

00:23:55 similar approach so that you could compete with approved inspectors? That was one of the prime

00:24:02 reasons, and if it hadn't have been for that introduction, LABC may well not exist in its

00:24:09 current format, because the private sector were able to promote that view because they were

00:24:21 working from Kent to Newcastle, whereas you'd got sort of numerous local authorities in between

00:24:30 there that might have a different view, and therefore it was an attempt, if you like,

00:24:38 having been thrown into the competition role to promote a view that the general public

00:24:52 could relate to. Yes, yes, thank you. You tell us in that paragraph that currently all local

00:24:58 authorities across England and Wales are members. Were all local authorities members of LABC between

00:25:05 2009 and 2015, do you know? As far as I'm aware, yes. Yeah, and then if we look at paragraph 18 at

00:25:13 the bottom of that page, you tell us, when I joined LABC it was a very small organisation of about eight

00:25:20 employees and its role was still being developed. It operated very much as an administration centre

00:25:27 with its primary function at that time being to help market local authority building control in

00:25:33 the face of competition from the private sector. A part of that function, and through me and

00:25:38 subsequent recruitment of additional staff, it would act as a collation point for inquiries and,

00:25:44 where appropriate, would offer opinions on particular issues for consideration by its members.

00:25:50 However, it has never been part of LABC's role to set or dictate policy. Now, when you say there

00:25:59 that its role was to offer opinions on particular issues, just to be clear, did that include issues

00:26:06 in relation to the correct interpretation and application of the building regulations and the

00:26:11 associated practical guidance? If we were asked for interpretation of

00:26:28 an approved document or whether a particular material was appropriate, then we were in a

00:26:38 position or tried to put ourselves in a position that could offer that opinion or find a member

00:26:44 that was able to do so. Yes, that's helpful. In general terms, what steps did LABC take to market

00:26:54 local authority building control? What kind of initiatives would it engage in to do that?

00:26:59 That's probably not a question that I should offer an answer to because

00:27:13 I was not a marketing person. That was not part of my role. If an organisation, another

00:27:25 professional organisation, wanted information or wanted a presentation, if you call that marketing,

00:27:33 I would go and talk to them about whatever information they were looking for.

00:27:39 But the problem that local authorities had when they were

00:27:45 tasked with entering a competitive market to offer what essentially was an enforcement service,

00:27:58 you can't sell enforcement, you have to provide something that people want.

00:28:05 That was the basis for LABC. Local authorities at the time they were forced into competition,

00:28:18 I don't honestly understand the legalities, but I don't think local authorities were

00:28:28 able to market a service or sell a service. This had to be done at arm's length.

00:28:36 And that is where things have grown from. I fully appreciate that marketing wasn't your primary

00:28:45 role there, but as you've said, this was quite a small organisation, so you must have been

00:28:50 generally aware of the initiatives that it was engaged in. Yes, and it was, there were,

00:28:59 again, moving on from the position that we were put in in 1985,

00:29:10 the arm's length organisation had

00:29:15 people who would go and talk to developers and try to persuade them to use local authority

00:29:26 building control where they were either using or trying to use the private sector.

00:29:37 And what were the particular selling features, selling points that people were trying to get

00:29:42 across about the advantages of local authority building control as opposed to approved inspectors?

00:29:49 That it was a, I'm struggling for the words, but it was a

00:30:07 unbiased service. It was not related in any way to the development in any way. It was

00:30:19 able to give a view that was not

00:30:26 to be seen as part of a development. It was an independent organisation

00:30:35 that would offer an oversight, and unfortunately, quite often people don't want that. It's a

00:30:43 difficult thing to sell. People, developers don't want you looking over their shoulder, so

00:30:50 how do you sell it? That's why I didn't market it, because to me that wasn't a role for

00:30:58 building control. Right, yes. And you talk there about the advantages of the, you say, the

00:31:03 independence of local authority building control. Can you remember any specific steps being taken

00:31:09 to protect the integrity and independence of local authority building control in the face

00:31:15 of competition from approved inspectors? I don't think that there was a need to

00:31:29 protect the independence, because that was a given through the local authority

00:31:36 employer and the legislative background. The difficulty that they had was having a product

00:31:47 to sell, having a service to sell, because it is the only regulated service within local authority

00:32:01 that has to compete on a job-for-job basis in the private sector or with the private sector.

00:32:08 Now you say in that last sentence that I just read out that it's never been part of LABC's

00:32:15 role to set or dictate policy, but I think you would accept, wouldn't you, that LABC did issue

00:32:24 technical guidance notes and consistency advice notes, which they may not be policy,

00:32:31 but they were certainly LABC's interpretation of the building regulations and the relevant guidance.

00:32:37 Yes. Yes. Now if we look at paragraph 22 on page 5 over the page,

00:32:47 you say this, you say it's also important to make clear that LABC is not a testing house,

00:32:52 and although it has been described as a certification body, that description is

00:32:56 potentially misleading. LABC issued certificates in respect of both K15 CoolTherm and RS5000,

00:33:05 that's the Cellatex product, but that should not be confused with the detailed testing and

00:33:10 a technical assessment of a particular product by an accredited laboratory comparable to an

00:33:16 organisation such as the BBA or the BRE. But it's right, isn't it, that LABC did issue certificates,

00:33:25 didn't it? It did, and certificates was the wrong word. Did you disagree with that word at the time?

00:33:33 Yes. Who did you make that clear to? It was,

00:33:40 it would not be documented, it would be a discussion between the,

00:33:49 myself and the chief executive probably. So with Lorna Stimson?

00:33:53 No, she wasn't the chief executive at that time. Who was it at that point?

00:33:57 Paul Everall. Right, yes. Now those certificates were issued

00:34:02 following a technical assessment carried out by the relevant research authority within LABC,

00:34:07 that's correct, isn't it? Yes.

00:34:12 And Mr Brennan has said in his witness statement that those certificates were then relied on by

00:34:21 manufacturers to illustrate that their product complied with the building regulations in

00:34:26 situations in which they had marketed their product. Was that your understanding as well?

00:34:32 I think understanding is a strong word. It's not something that

00:34:45 perhaps describes it the way that I would. It was a way that manufacturers could

00:34:52 get an insight into the potential for acceptance of their products with

00:34:59 local authorities because it was the local authority, individual local authority, that had

00:35:05 to approve a project on the building regulations, not LABC.

00:35:12 Yes, but you must have been aware, surely, and I think we'll come to some examples of this,

00:35:17 of manufacturers using LABC certificates as part of their marketing materials.

00:35:24 Yes. Yes.

00:35:25 And it's right, isn't it, that the LABC issued several certificates through both the type

00:35:35 approval scheme and subsequently the registered detail scheme for the K15 product. We'll come

00:35:41 back to that, the Kingspan product. Now we're going to discuss these schemes in more detail later,

00:35:46 but can you just explain to us, just in general terms, what was the type approval scheme

00:35:52 within the LABC?

00:35:57 I can give you an overview. Yes.

00:36:00 I can't give you a detailed view because I was not involved on a day-to-day...

00:36:05 That's fine. An overview is fine. ...basis with it. But essentially,

00:36:13 a product to be used within a construction project needs to satisfy the requirements

00:36:21 outlined in approved documents. It's not always easy to trace all the documents that they need

00:36:30 to satisfy and indeed whether there is evidence to show that they satisfy those requirements.

00:36:40 The type approval, registered detail, call it what you will, that that process was to

00:36:50 look in detail at the evidence provided by the manufacturer to see whether it matched

00:37:00 what was being recommended in the approved document and to produce a document to say that

00:37:08 we've looked at this and in this given circumstance there is reason to expect it to satisfy the

00:37:17 requirements. Yes.

00:37:19 So would it be right to understand that in effect LABC carried out the investigation

00:37:27 into a particular product, that it might carry out if it were being done by a building control

00:37:33 officer in order to satisfy itself that the product would comply with ADB?

00:37:41 No. LABC would not. This is done by members. It's not done by me or an employee of LABC.

00:37:57 It's a member support whereby

00:38:01 it can take a lot of time to pull together the amount of

00:38:13 evidence necessary to show whether something satisfies the requirements indicated in an

00:38:19 approved document and to save time for a manufacturer having to go to 320 different

00:38:31 local authorities and produce all this documentation every time, assuming they wanted to do development

00:38:37 in those 300, but a developer would want to work in more than one local authority area

00:38:45 and this was the difficulty that local authority had in persuading that developer to use their

00:38:52 service in the first place because that developer could go to the private sector

00:38:59 and get that opinion once for wherever that was being used. So to try and get back to the consistency

00:39:09 was to pull together the documentation necessary to show or to provide evidence

00:39:21 that compliance with building regulations can be met. The manufacturer then knows pretty much

00:39:30 what evidence he might be asked for by 10 different local authorities rather than having to go to 10

00:39:38 different authorities. Also those authorities have got an idea of what documentation they might need

00:39:44 to look at as well. But in a sense the LABC certificate reflected the, forget who carried

00:39:54 it out, whether it's one of your employees or someone from a member authority, reflected the

00:40:00 investigation that a building control surveyor would need to undertake to be satisfied that the

00:40:08 product conformed to ADB. That's its point. I think that's a fair description. Thank you very much.

00:40:17 No, that's very helpful. Thank you. I'm just interested to know what in practice, what effect

00:40:25 those certificates then had as far as you understood it because you just referred to the fact you said

00:40:31 that the manufacturer would then know what documents they might need to produce. Wasn't the effect

00:40:38 much more immediate than that? That in effect once you've got the LABC certificate for the product

00:40:44 it would then be fast tracked through the building control process on particular projects?

00:40:51 That might well have been the effect. It was not necessarily the, or my belief of the way that

00:41:04 that evidence should be used because invariably the manufacturers were told individual local

00:41:12 authorities will be the ones issuing an approval. But I think it's fair to say that

00:41:24 there was a degree of inference that a particular type of construction would be satisfactory.

00:41:34 And you were aware of that effect at the time that you were in that senior technical role?

00:41:39 Yes. We'll come back to that because in the context of K15 we see some descriptions provided

00:41:46 as to what the effects were of the certificate. Can I look now at paragraphs 24 and 25 while we're

00:41:53 in your statement on page six for just some more background to these system type approval and

00:42:00 registered details certificate systems? And if I want to look at 24 and 25 you say system approval

00:42:07 had already existed between local authorities in advance of the creation of LABC by virtue of a

00:42:13 unilateral agreement between local authorities to work together and recognise each other's

00:42:18 technical decisions to ensure consistency. This was well in advance of the introduction of

00:42:23 competition into building control in 1985. And then you tell us 25 within this process one

00:42:29 local authority would technically examine a particular construction system or product

00:42:33 by interrogating the information provided to them by the manufacturer together with supporting

00:42:38 certification and test results provided to the local authority by the manufacturer from recognised

00:42:43 bodies, BBA, BRE etc. When the local authority was satisfied with the information provided a second

00:42:50 local authority would review the findings and where appropriate verify these to allow for national

00:42:56 recognition. So just to be clear you're describing there the fact that this system had effectively

00:43:02 been going on for many years informally within LABC is that correct? Not within LABC because

00:43:09 LABC didn't exist. Sorry across local authority building control departments this sharing of...

00:43:16 There's always been a need to know what your neighbour is doing and what your neighbour

00:43:22 may think of a particular project and even in my sort of early years within the profession

00:43:34 long before the days of emails and computers there was a need to speak to adjacent authorities

00:43:43 to see what their view was and indeed there was there was quite often more regional meetings

00:43:50 and talks for such discussions to take place and this has developed from that. Yes that's very

00:43:57 helpful thank you. Now I want to turn now to look in more detail at the Kingspan K15

00:44:04 certificates that were issued by the LABC and you've helpfully exhibited to your statement

00:44:11 as well as Mr Brennan prepared it's at LABC 0019607 and I want to look at page two.

00:44:24 So this is an exhibit to your statement and here at page two we helpfully see a table which sets

00:44:31 out all the certificates that the LABC issued for K15 between 2009 and 2019 that's right isn't it?

00:44:40 Yes. Yeah and we can see there that the first certificate that was issued was called a we can

00:44:49 see it from the third column along in the top row an LABC type approval certificate and that was

00:44:57 valid between the 1st of May 2009 to the 30th of April 2012 that's correct isn't it? I have to

00:45:06 accept that because I didn't prepare the document and I didn't prepare the certificates either so

00:45:14 this document is prepared by someone other than myself. Yes I appreciate that I'm going to take

00:45:19 you to what involvement you did have in that type approval certificate in due course at the moment

00:45:25 I'm just trying to get the broad chronology out there so we've got that type approval certificate

00:45:33 and we can see it's signed by David Jones of Hereford's accounts and we heard from Mr.

00:45:38 Jones in module two of the inquiry's work and then

00:45:49 the process for that type approval service was set out in the LABC type approval manual that's

00:45:57 right isn't it? Yes. Yeah and we'll look at that in due course and then we can see on this table

00:46:04 that the next certificate that was issued for K15 was the registered LABC registered details

00:46:10 certificate it's called RD165 in the second row down and that was issued on the 28th of August

00:46:18 2013 and ran to the 28th of August 2014 do you see that? And it tells us here that that certificate

00:46:26 was signed by you is that correct? It would be an auto signature it was not sort of a document that

00:46:34 I had any direct involvement with. Okay well again we're going to come in detail to look at the

00:46:40 email exchanges and other correspondence around that certificate now that registered details

00:46:46 scheme that was a new scheme which replaced the type approval scheme is that correct?

00:46:50 Yes the again I sort of reiterate I don't have direct involvement with

00:47:04 the changes that have been made there was a working group that put this together which I didn't attend

00:47:12 and so the the change in names that have gone through the iteration

00:47:22 is a development to try and reflect more accurately what would what's trying to be

00:47:28 achieved as much as I understand. Yes I understand just at this point I want to see if you agree

00:47:34 with what one of your colleagues said about the registered details scheme to Kingspan if we can

00:47:39 pull up an email this is labc303024 and I want to look at this top email this is from somebody

00:47:55 called Sam Lee Muller within labc to Reshma Rudaman of Kingspan on the 14th of July 2015

00:48:05 and I want to look really at the bottom of this email there's some red text and five lines up from the bottom

00:48:18 we can see in the middle of a page a sentence which says this an labc registered detail is

00:48:24 designed as a fast track route through the building regulation process and can significantly reduce

00:48:31 the time and costs associated with a construction project. Do you see that there? Yes. Do you agree

00:48:38 with that description of the registered details system? I can see why someone would want to say that

00:48:49 and

00:48:50 and

00:48:57 I think it's a description that that I would

00:49:04 not word in quite the same way. I see so if you'd seen somebody one of your colleagues describing

00:49:10 the registered details system in that way would you have disagreed with them?

00:49:14 We would possibly had a discussion.

00:49:28 We're very much aware now that we were perhaps not aware at the time of how wording can be

00:49:39 so important and so I think my view now is probably different to what it would have been at that time.

00:49:46 I see thank you. Can we just clarify one thing? I infer from what you've said already that there

00:49:54 wasn't really any change of approach between the type approval scheme and the registered detailed

00:50:01 scheme. The same technical analysis was going on. Correct. Yes thank you that's helpful.

00:50:09 If we just go back to that table then back to labc 0019607 we can see that there was another

00:50:17 registered details 165 certificate for k15 published on the 21st of august 2014 which ran to the 31st

00:50:26 of october 2014. Do you see that? Yes. And again that's said to have been signed by you and we'll

00:50:33 see that in the certificate in due course yes? Yes. And then the next certificate was dated the

00:50:39 8th of january 2015 which we're told in the final column on the right labc comment these certificates

00:50:47 were not published but were sent to kingspan and should be considered as delay in publication down

00:50:52 to kingspan waiting an updated corrected report from the bre and then in the next row down we can

00:50:59 see there was a another registered detailed certificate issued on the 30th of march 2015

00:51:04 that ran to the 30th of march 2016 and then in the final line we can see there was another

00:51:09 certificate from march 2016 through to march 2019 is that correct? I have to accept that as correct

00:51:19 because as i've said i did not prepare this document and so whilst it's part of my statement

00:51:29 it is a declaration by labc not necessarily by me. I see but it's a fact isn't it? As far as i'm aware

00:51:38 i've no reason to disbelieve it. No thank you. Now i want to start by asking you more detail about

00:51:44 the system approval certificate that was issued in may 2009. Now if we start with that labc type

00:51:52 approval certificate if we can go to kin 405705 here we've got that certificate we can see from

00:52:09 the top box certificate holder. Sorry if we could just zoom in on the top we've got it's for kingspan

00:52:17 installation and then under that under part two system title description is for kingspan

00:52:24 kingspan cool therm k15 rain screen board and it says underneath that systems have been assessed

00:52:32 on the following drawings and then there's a list and then underneath that

00:52:35 sorry we just need to go back to that there is a heading drawings and documentation to be referred

00:52:42 to and it's got the herifitia council type approval summary third of march 2008 kingspan

00:52:50 publication for k15 and then the bba certificate from october 2008 do you see that? Yes. And then

00:52:59 we can see under assessment section four there the design and method of construction of the system

00:53:10 designed in two above has been examined and as as far as it has been shown has been found to be

00:53:17 capable of complying with current building regulations and then we can see this has been

00:53:23 signed by david jones at herifitia council from the bottom of the page and then if we go to page

00:53:30 three of this certificate if we look at in the overview first at the top of that page

00:53:40 we can see it says cool therm k15 is a rigid phenolic insulation board incorporating foil

00:53:46 composite facings and then it says what it's intended to be used for and then if we

00:53:58 go over the page to page four

00:54:06 we can see under requirement b fire safety considerations if we could zoom in on that

00:54:12 it says k15 has been tested in accordance with and we see a bs 8414 part one test

00:54:20 we then see some fire resistance tests a 476 part six and part seven tests

00:54:28 and then underneath that it says this it says from the results it can be considered as a material

00:54:34 of limited combustibility and meets the criteria for class nought classification for surface spread

00:54:41 of flame do you see that on the page and then on the top of page five over the page

00:54:52 we can see under requirement b for external fire spread it says since k15 can be considered a

00:54:59 material of limited combustibility it is suitable for use in all situations shown on diagram 40 of

00:55:05 approved document b volume 2 including those parts of a building more than 18 meters above ground

00:55:14 now so that's what this first certificate said if we can look at what you say in your witness

00:55:21 statement paragraph 70 on page 23 of your statement

00:55:24 you're asked about this in your statement and you say this this is principally a matter for mr jones

00:55:32 i should make it clear that labc's position is that it does not claim that k15 was in fact

00:55:37 a material of limited combustibility or could or should have been described as such and i agree with

00:55:43 that i understand this is also now conceded by king span now i just want to be clear presently

00:55:51 what you are saying in that part of your statement are you accepting that it was an error

00:55:55 in the certificate to say that it could be considered a material of limited combustibility

00:56:01 yes and so you accept that the certificate was inaccurate and misleading yes

00:56:10 yes

00:56:16 were you aware in 2009 that k15 was not a material of limited combustibility

00:56:24 i'm not aware that i was asked that question in 2015 and therefore i may or may not have been i

00:56:36 can't answer the question i see it was 2009 2009 i beg your pardon yeah um

00:56:45 i can't answer that question with any degree of of recollection to be perfectly honest okay let's

00:56:53 look at some correspondence then between herafordshire council the labc and king span

00:56:58 which explains some of the background how this certificate came to be issued if we can go to

00:57:03 labc 30s 2281 and look at page four to start with

00:57:17 we can see that this is an email from andrew pack sorry if we could just blow it up thank you

00:57:23 this is from andrew pack of king span sent to you on the 24th of november 2008

00:57:30 and we can see he says dear barry thank you for your email i've tried you a couple of times this

00:57:35 morning i'd be grateful if you could ring me when you are free now can you help us was this the

00:57:43 first contact from king span requesting that k15 be assessed by the labc that email has got nothing

00:57:53 to do with k15 it is headed tapered roofing guidance well if we go up the tape of roofing

00:58:04 guidance is about the thermal performance and the way that you calculate if i remember correctly

00:58:15 this correspondence was about how to calculate the u value of a flat roof when you're using

00:58:24 tapered insulation it has got nothing to do with a particular material or the the

00:58:33 fire resistance or it was thermal properties in its entirety that is the reason for this

00:58:40 i see well let's just go up the chain if we go to page three of this same chain we can see an email

00:58:48 from you to philip hamond now is it right that he was the national director of business development

00:58:55 yes and it's copying in launas stimpson and bill harrison yes yeah what role was launas

00:59:05 stimpson at the time we know she's been chief executive since 2019 i couldn't swear to the

00:59:14 particular job title but it was more about promotion and marketing of of the service at

00:59:20 that time yes and then you've also copied in phil harrison he was the business development

00:59:25 director at labc is that correct he was a part-time i don't mean this is a derogatory

00:59:33 term but he was a part-time salesman for for labc yeah and you say in this email hi all you may be

00:59:40 aware of the work we've done recently with kingspan on a technical guidance note for tapered roof

00:59:45 insulation and in the next paragraph you say this i have now received an inquiry from their technical

00:59:51 services manager andrew pack for information on gaining a sta is that system type approval

00:59:58 or similar for their cool firm k-15 rain screen product primarily with regard to compliance with

01:00:05 parts b and c of building regulations from initial discussions i believe there is scope for us to

01:00:11 consider a system type approval in this situation given that the product has relevant bba certification

01:00:17 etc and we can add to that an opinion on compliance with building regulations in situations to be

01:00:24 described by kingspan could i ask the business development team to pick this up and discuss

01:00:29 arrangements with andrew and consider a suitable la local authority link do you see that yes so

01:00:38 it was on that basis that we had understood that your conversation with andrew pack

01:00:43 whilst you'd had these previous dealings about tapered roof insulation was in fact about

01:00:49 um a system type approval for the k-15 product do you see that would be

01:00:57 i would say the first time it was ever mentioned yes and can does this help prompt your memory

01:01:06 about what you discussed with kingspan when they were raising this point about k-15 and system type

01:01:12 approval the whole process and my connections with kingspan were developed through

01:01:25 um mhclg or dclg or whatever they were at the time working groups looking at the thermal

01:01:35 performance of buildings because the the working groups at that time were all about thermal

01:01:40 performance and sustainability and um that is how i came to to know these people and and the

01:01:50 reason that the the emails are worded in the way that they are in a friendly manner because we sat

01:01:56 on the same working groups um their technical expertise um and i came about the discussion

01:02:06 because there was some challenges there was some difficulty because it this wasn't something

01:02:15 in an unapproved document there was some difficulty in actually how to calculate the thermal

01:02:20 performances that that were being talked about at the time that was my involvement with them

01:02:26 they used that connection to uh from to go through me to start this process yes moving yes that's

01:02:37 very helpful background to this um but but can you tell us any more about what you actually

01:02:42 discussed with mr pack at this time it looks like you've had some initial discussions because you

01:02:48 say i believe there is scope for us to consider a system type approval in this situation so it

01:02:54 looks like you've expressed some kind of um view or certainly internally you were my when

01:03:00 anyway in my role within local authority when anybody came to me with a product that i'd never

01:03:08 heard of or not seen before was does it have a bba certificate does it does it meet the

01:03:17 the requirements laid down i can only infer from from the information there that i've asked that

01:03:26 question and they've said yes um having said yes if there is if if they had indicated that there

01:03:36 was certification in place um by an independent regulated authority such as bba bre etc which is

01:03:51 what we would be looking for because as i've also said in my statement we were not a testing house

01:03:58 to look at um new products we needed the scientific evidence provided by others

01:04:06 we're not scientists yeah that suggests that they said we've got that and in which case um

01:04:12 there may be a way to move forward okay let's look up at carrying on with this email chain to page

01:04:18 two we can see here there's an email from phil harrison to chris jenner of harrifordshire council

01:04:25 on the 26th of november 2008 that's at 10 14 yes and he says good morning chris thank you for

01:04:32 agreeing to take on this system approval for kingspan as you probably already noticed andrew

01:04:38 pack's contact details are at the foot of this string of emails attached as agreed for ease of

01:04:43 reference is a pdf of the type approval service manual together with a copy of the certification

01:04:49 flow chart please let me know if you need anything more and then um on the same day

01:04:57 we can see this uh from the email actually below this at the bottom of page two and onto page three

01:05:03 there's an email of the 26th of november 2008 um phil harrison wrote back to andrew pack saying

01:05:11 good morning andrew further to our conversation yesterday and then over the page harrifordshire

01:05:15 council have kindly agreed to act as the matched authority to check your proposed system approval

01:05:21 application and chris jenner their building control manager will contact you shortly to

01:05:25 arrange an initial meeting and then if we look at the bottom of page one of this string

01:05:36 there is an email from david jones to phil harrison

01:05:39 and uh he says this i've been following up on your email below with regard to a type approval for

01:05:45 kingspan's rain screen cladding insulation board and if i understand the process correctly i now

01:05:49 need to pass it back to labc for an invoice to be raised i met with andrew pack before christmas

01:05:56 to discuss what we could offer them through the type approval scheme and suggested that

01:06:01 in view of the scope of the certificate the minimum fee of 500 pounds would be adequate

01:06:06 would be adequate he was keen to proceed with this after our meeting and so i've carried on

01:06:10 and done the necessary work to produce the certificate though i haven't forwarded anything

01:06:14 onto andrew as yet and then he says this the most we can really offer in this case would be a product

01:06:21 approval k-15 is just the insulation component of the rain screen walling system both the inner

01:06:28 structural frame and the rain screen cladding itself are unknown variables produced by a third

01:06:32 party and so a system approval would be impossible to pin down i did emphasize this to andrew to be

01:06:40 clear that this type approval would not go any further than the current bba certificate but he

01:06:45 was happy that it would still be worthwhile if only to get the labc seal of approval

01:06:52 and then he carries on i would suggest then that the type approval certificate be for k-15 as part

01:06:57 of a generic but undefined system and refer to the following documents and then he's got

01:07:05 the documents listed and if we go over the page that includes the bba certificate and kingspan's

01:07:10 own literature and he says i'll be grateful if you could let me know what the next step would be to

01:07:15 formalize the approval now i appreciate that was an email to phil harrison from david jones you're

01:07:23 not copied in on that email but we want to know were you aware that mr jones in that email had

01:07:30 expressed some concerns about using a system approval process rather than a product approval

01:07:37 for k-15 no so you were never made aware of that not to my knowledge or not to my recollection

01:07:46 mr jones gave evidence to this inquiry and his evidence was that he spoke with someone at the

01:07:52 labc possibly mr harrison before he agreed to take on the job of assessing k-15 were you ever

01:07:59 made aware of any such discussion no were you aware about whether mr harrison might have reassured

01:08:08 mr jones that it was okay to use the system approval process

01:08:14 no did you ever give any reassurance to mr jones that it was okay to use the system approval process

01:08:21 for k-15 as far as i can recall i've never spoken to mr jones right now if we go up the page

01:08:30 we can see at the top of page one there's a response from mr harrison this is now on the

01:08:36 ninth of january 2009 and and he says to mr jones good morning attached for your use as agreed are

01:08:46 the latest versions of a type approval application form and the compliance declaration thank you

01:08:51 for sorting this out so thoroughly do you see that yes and then if we can look at another email

01:08:59 kin 3024989 if we go in the second half of that page we can see an email from david jones to

01:09:15 andrew pack of the 26th of january 2009 and he says this dear andrew apologies for being a while

01:09:22 getting back to you despite the slowdown things have still been a bit hectic since we last met

01:09:27 and he goes on i've now done the necessary the research necessary and come up with what i think

01:09:33 will be a usable certificate for acceptance by labc across the uk what i have tried to do as

01:09:40 we discussed is to get away from just assessing k-15 as a product in isolation

01:09:46 and extend the certificate to represent a system approval for the whole external wall arrangement

01:09:53 of course with the other components being undefined and with various options available this

01:09:58 does present some problems as we established when we met what i've done though is to refer to the

01:10:03 three standard details contained within the king span literature unless you've got any other

01:10:08 standard drawings that you think may be more appropriate and instead of applying a manufacturer's

01:10:13 reference to the undefined elements i've specified a generic standard for each and then he goes on

01:10:18 the conclusion being that k-15 can be accepted in all locations provided the other parts of

01:10:24 the wall construction meet the standard stated and reflect the king span standard details

01:10:32 and then he goes on to what he describes in the next paragraph as the painful part and he's talking

01:10:37 about money and how much is going to be charged for that certificate and he said once that's done

01:10:45 and the money's been paid i can send over the draft approval statement so you can make comments

01:10:50 if you wish now were you ever made aware that mr jones had had this discussion with king span

01:10:57 about the system the certificate being issued for a system rather than a product i have no

01:11:03 recollection of it no and thereafter what the correspondence shows is that a draft certificate

01:11:11 is sent from david jones to the labc if we can go to labc three zeros two two nine four

01:11:19 four

01:11:28 the email here we go at the top of the page we can see david jones on the third of march 2009

01:11:36 sends to sasha cruise was sasha an administrative assistant at labc she might well have been the

01:11:44 technical coordinator that you referred to earlier right yes that's helpful yeah

01:11:50 so she's pulling together the administrative work on this certificate yeah yeah and he says

01:11:57 further to your email below in the type approval application from king span please find attached an

01:12:02 electronic copy of the type approval compliance declaration along with the three documents which

01:12:07 should accompany the type approval certificate because of the limited room on the form itself

01:12:12 the relevant issues have been summarized on the separate summary document and that's the document

01:12:16 we looked at which says k-15 can be considered a material of limited combustibility yes and it

01:12:23 says the draft copy of this has been forwarded previously to phil harrison at labc and andrew

01:12:29 pak at king span and following their comments should now be ready for formal issue

01:12:33 thank you

01:12:37 now can you help us as to whether mr harrison had approved the contents of the draft certificate

01:12:45 and the type approval summary he's clearly been sent it previously can you help us on that i've

01:12:50 no recollection of having seen these documents before at all i'm sorry can you help us as to why

01:12:56 you as head of technical or key you know key role of technical weren't being sent this draft

01:13:02 certificate so you could check that the technical content was was accurate the

01:13:10 there should have been a peer review process which is the way that i've always understood this

01:13:17 to to work i think because of the the limited numbers of people that we had at labc there was a

01:13:33 a degree of reliance on individuals sort of to

01:13:42 carry out their job in the best way possible and i was

01:13:52 likely more involved with other aspects of of things going on and not in a position to review

01:14:00 daily things of this nature now had there been a

01:14:11 a consideration that it needed to be taken further it would be up to those people to bring it to me

01:14:20 as far as i'm aware that didn't happen yes well we can't see the draft certificate being sent to

01:14:26 you but let's let's go forward with the story if we go to labc 308171

01:14:37 and i want to look on page two

01:14:44 here we can see that sacha cruise on the 3rd of march 2009 sends to you and to others we can see

01:14:55 somebody called john gavin gavin at decorum borough council mr allen at guinard council

01:15:01 mr pathlin and west norfolk lorna stimpson and north harris hartford district council they're

01:15:08 all there on the email list and it says this to all members of the type approval working group

01:15:15 dear colleague please find attached a pdf of the completed compliance declaration form for the

01:15:20 system type approval for kings band insulation for your approval please could you advise me

01:15:25 of any comments in your approval by return email no later than tuesday the 17th of march

01:15:30 i look forward to hearing from you in due course now we can see you're on this email

01:15:39 were you a member of what's being referred to here the type approval working group

01:15:44 this would be the peer review group that i referred to earlier i couldn't have named the people on it

01:15:55 and as a member of staff as opposed to everybody else on that list apart from lorna

01:16:05 and lorna sasha paul everall but they the other members were the

01:16:16 local authority representatives who effectively were the the peer review group

01:16:23 and we as staff were there to do their reckoning if you if for want of a better description

01:16:32 so i would not comment directly unless asked to do so by a member of that group right so even

01:16:39 though you're being sent this email are you saying that you weren't actually a member of this type

01:16:45 approval working group i attended it as a member of uh as a member of staff so does that mean you

01:16:53 wouldn't have looked at the information i was sent the information as a matter of courtesy

01:17:01 and would not unless someone raised an issue necessarily review every document that was

01:17:09 circulated right do you have any recollection of reviewing the k-15 documentation at around this

01:17:16 time in no i don't 2009 no and um can you just help me what then was the purpose of this group

01:17:26 the type approval working group was this effectively a peer review process for the

01:17:31 situation yeah this was an opportunity for somebody to raise questions

01:17:36 and those questions would most likely have been referred to myself

01:17:49 now if we look at this email and we can see that it's saying the completed compliance declaration

01:17:55 form is being sent for the system type approval now we find that at hbc six zeros 21

01:18:06 on page two

01:18:16 so here we can see the compliance declaration and if we look down this page we can see

01:18:25 that it includes the document and drawing list if we go down the page it's got drawings documentation

01:18:33 here for to council time approval summary third of march 2008 the king span publication and the

01:18:40 bba certificate now those supporting documents don't appear to be attached to the email that

01:18:52 miss cruise sent can you help us as to whether the type approval working group would have been

01:18:57 sent those important supporting documents when they were sent this certificate

01:19:04 i can't confirm or otherwise i wouldn't know would you have expected them to have seen

01:19:09 the supporting documentation which underpinned the certificate

01:19:17 i would expect them to have access to them doesn't necessarily mean they needed to be

01:19:24 circulated with with this i see would they have access to them through a shared document library

01:19:35 most authorities 2008 most authorities i think at that time

01:19:44 would have electronic access to bba certificates

01:19:51 uh the king span information i can only assume would be available on their website yes but the

01:19:56 herafordshire council type approval summary was a pretty important document because that was the

01:20:00 one that set out in detail how it complied with the building regulations yes i would have expected

01:20:06 that to be circulated yes

01:20:08 yeah

01:20:13 and then if we go on with the story if we go to labc 308171 and look at the top of page two

01:20:28 we can see at the top of page two there's an email of the third of march 2009

01:20:32 at 1427 sent by mark pafflin from west norfolk to sasha cruz and to you and to others and he says

01:20:42 this i have no particular issue with this other than why is it an why is an insulation board a system

01:20:51 and then um we can see one email up at the bottom of page one mr fullstone from north hartfordshire

01:20:59 north hartfordshire

01:21:03 if we go one email up yes it starts right at the bottom of that page fourth of march 2009 mr

01:21:09 fullstone says difficult one to call this the certificate refers to a series of other documents

01:21:17 including a county issue i am happy with the assessment of the design by the local authority

01:21:23 presumably the thickness depends on whether it's assessed under l2b or l1a referring to part l

01:21:31 i agree with mark as this is an insulation product that could be used at various thicknesses

01:21:35 is this a system or a product do you see that yes and just going back to the bottom of page

01:21:41 one you were sent that email we can see yes do you know what he meant by it includes a county

01:21:50 issue is that merely because there's a type approval summary from herafordshire i think the

01:21:58 references there are all related to the thermal performance of the material particularly as he's

01:22:08 referring to thickness uh the relation referring to part l is thermal performance the county issue

01:22:18 um i'm sorry you'd have to go back was it herafordshire well herafordshire with the

01:22:23 lake no i don't know where the um the county issue was likely one one area i had a particular

01:22:37 um interest in thermal performance of materials and they produced their own

01:22:46 guidance notes on thermal performance um and various thicknesses and i suspect that is what

01:22:54 that reference is about right but it's not they're not just talking about thermal performance there

01:22:59 are they they're both saying both mr pafflin and mr fullstone are saying why is this a system

01:23:05 approval not a product approval because this is a product and it could be used in a variety of

01:23:11 different systems they're raising that very clearly aren't they there they are yes but i

01:23:17 still say the inference from that is it's all about the thermal performance of the material

01:23:24 and that is why it would be a a product i see and that's how you understood it at the time is it

01:23:31 right well that that's my sort of recollection now whether that's where i understood it at the time

01:23:38 i can't be certain right and we can see miss stimson one email up we've got it at the top

01:23:44 of that page responds the same day she said could this be an adopted solution or whatever it's

01:23:50 called this week now adopted solution would be for a product wouldn't it not for a system yes

01:23:57 not even sure we had product approvals or these are people that are on the the market inside

01:24:09 of labc that or laura was at that time anyway and that's rather a

01:24:20 that's just an off the cuff remark which really i can't comment on yes well we'll look at the

01:24:24 manual in a moment it would appear that there were product type approvals at this time we'll

01:24:28 have a look at the manual and can you recall anybody ever responding to mr pavelin or mr

01:24:35 fullstone explaining why this product was being granted a system approval no and did you ever

01:24:45 express any view about this at the time despite being copied or sent these emails no there was

01:24:53 reference within the documentation to the certification which i would have expected

01:25:00 and therefore i either bba certificates and therefore i would not have

01:25:08 likely looked at it in any greater depth right mr term and i think that's a good moment for our

01:25:13 morning break if that's thank you yes i think it's time we had a break well mr tanner we're going

01:25:18 to have a short break now we'll resume please at 20 to 12 and on this occasion and whenever you

01:25:26 leave the room i have to ask you please not discuss your evidence or anything relating to

01:25:30 it with anybody else all right thank you very much would you go to the usher please

01:25:48 all right 20 to 12 please

01:26:18 you

01:26:48 you

01:27:18 you

01:27:48 you

01:28:18 you

01:28:48 you

01:29:18 you

01:29:48 you

01:30:18 you

01:30:48 you

01:31:18 you

01:31:48 you

01:32:18 you

01:32:48 you

01:33:18 you

01:33:48 you

01:34:18 you

01:34:48 you

01:35:18 you

01:35:48 you

01:36:18 you

01:36:48 you

01:37:18 you

01:37:48 you

01:38:18 you

01:38:48 you

01:39:18 you

01:39:48 you

01:40:18 you

01:40:48 you

01:41:18 you

01:41:48 you

01:42:48 all right mr tanner you're ready to carry on i hope thank you very much yes sir strange yes thank you

01:43:15 yes i want to look at the type approval manual now we mentioned that earlier if we can go to hbc 6049

01:43:31 and if we look at page six

01:43:36 which is where this starts here we've got the labc type approval service manual

01:43:42 that's the front page and we can see from page seven that it's dated march 2006 there we go edition

01:43:49 three march 2006 and if we go to page 10 and section 2.2 of this manual we see at the bottom

01:44:00 it's got different categories of type approval just zoom in on that and it says

01:44:08 a certificate shall be granted under one of the following four categories which category is chosen

01:44:13 will depend upon the most obvious categorization that the particular case naturally falls in

01:44:19 if there is any duality of fit then the customer may choose i think that's supposed to choose and

01:44:24 then we've got underneath that house type approval and then if we go over the page

01:44:31 building type approval that covers complete standard designs for whole buildings

01:44:39 underneath that we have the system type approval and we can see under the first paragraph it says

01:44:45 this category covers modular building systems elements and components that can be used for

01:44:51 or form part of different building designs and configurations it also includes for temporary

01:44:56 structures of any variety so it's elements and components that can be used for or form part of

01:45:04 different building designs and configurations yes and then underneath that we have the product type

01:45:15 approval and it says there this category verifies product small components in respect of compliance

01:45:22 small components in respect of compliance with specified building regulations it can be applied

01:45:28 to any construction product that in itself is subject to the building regulations or that

01:45:32 contributes to or has an influence upon compliance with building regulations now looking at that that

01:45:39 was the the categorization you had in place at the time according to the manual can you explain to

01:45:45 us why a system approval certificate was issued for k-15 despite the concerns that had been raised

01:45:51 by mr paffling and mr fullstone as members of the the working group i'm sorry no i can't

01:46:02 and you know that was a discussion i wasn't part of wasn't the only appropriate option

01:46:10 for the certification of a product like k-15 a thermal insulation board a product approval

01:46:18 um a product approval could have been appropriate in cases for providing additional insulation to

01:46:34 single-story domestic dwellings for argument's sake not necessarily in the type of situations

01:46:40 that's under review here

01:46:45 right let's look at some more correspondence i'm sorry before we leave this document can we

01:46:50 can we just scroll up to system approval yes

01:46:56 i mean the opening paragraph to system approval

01:47:02 suggests that it is or may be appropriate for individual elements of a design

01:47:11 um and the third paragraph notes that the category is exceedingly wide

01:47:18 accommodating everything from whole building systems through to individual components

01:47:23 now i don't understand at the moment and perhaps you can help us why an individual component

01:47:31 properly falls within the range of system approval

01:47:37 i'm inclined to agree with you i don't understand it either

01:47:42 but take it you weren't responsible for formulating this no um i was not party to the

01:47:51 the wording of this document so i'm sorry i'm i'm gonna go on you can't explain it no all right

01:47:55 thank you very much yes thank you um if we look at the correspondence again um if we go to la bc

01:48:03 20319

01:48:13 we can see an email to you

01:48:16 um so this is after launer stimpson has said on the 9th of march 2009 in that second email

01:48:23 down could this be an adopted solution or whatever it's called this week and then sasha cruise on the

01:48:29 26th of march 2009 emails you hi barry can this be issued thanks sasha now it appears that you

01:48:37 didn't respond to that email i think you tell us that in your statement is that right i have no

01:48:43 recollection of doing so and then you get a further email from miss cruise if we go to la bc 308171

01:48:59 it's at the top of the page it's on the 21st of april 2009 copying in mr harrison and mr jones

01:49:08 to you hi barry i've spoken to david jones at herifordshire regarding kingspan insulation

01:49:13 limited can you please advise me regarding the issuing of the certificate david has said that

01:49:19 conversations took place in the initial stages of the application as there were concerns then as to

01:49:24 whether this was a system or product it was agreed then that it was a system and for the

01:49:29 application to go ahead david is getting pressure from kingspan for the certificate now so could you

01:49:35 please let me know as soon as possible as to whether i can issue the certificate do you see that

01:49:42 yes do you remember being consulted about whether this certificate could be issued

01:49:47 i have no recollection of that correspondence but it was obviously sent to me yes and we know the

01:49:57 certificate was issued in the terms which mr jones had proposed can you help us as to whether there

01:50:04 was ever a response to this email we can't see one in the documents i know i can't i i have no

01:50:11 recollection of any response i may have given you can't recall no should there have been a response

01:50:20 to this for the certificate to then be issued there should have been

01:50:29 but i can't say whether there was or there wasn't i'm sorry i have no recollection and there's

01:50:34 obviously no record of it i don't know we can see in the documents that the certificate was sent to

01:50:39 mr jones on the 1st of may 2009 by miss cruz we can see that uh labc 301882 page three

01:50:57 she sends him a letter dear mr jones please please find and close the system approval

01:51:01 certificates that you requested for kingspan insulation limited

01:51:06 um now just on this theme can we just look at what you say at paragraph 58 of your statement at page 20

01:51:19 you say this in your witness statement apart from an initial discussion with andrew pack

01:51:26 and an email sent to me by sachet cruise querying whether k-15 was a system or a product which i do

01:51:32 not appear to have responded to i have no knowledge or recollection of any involvement

01:51:36 or of other labc staff members involvement in the 2009 k-15 assessment as explained above at that

01:51:43 time the role of labc was essentially administrative i understand from the documents

01:51:49 disclosed the inquiry that sachet cruz of labc notified the peer review panel members

01:51:53 of the need to review the k-15 assessment and subsequently sent the certificate to mr jones

01:51:57 on the 1st of may 2009 for him to sign and then send to kingspan directly with a copy being returned

01:52:03 to labc miss cruz held the title of technical administrator but essentially her job was purely

01:52:09 administrative she is no longer employed by labc now what do you mean when you say in the middle of

01:52:16 that paragraph at the time the role of the labc was essentially administrative

01:52:22 i would have hoped that it was self-explanatory but it was well you have a technical working group

01:52:31 sorry yeah it was the the the technical working group was made up of people employed in local

01:52:42 authority not members of staff so the the members of staff were there to coordinate the the thoughts

01:52:50 and processes of of those members of the working group i see so it's on that basis the committee

01:52:58 it was a committee of members from local authorities yes and the committee was the committee of the

01:53:06 so it's on that basis it was a committee it was a committee of members from local authorities

01:53:11 yes i see so it's on that basis that you're saying you had very little involvement with

01:53:16 the certificate is that right yes i see now you tell us paragraph 75 of your statement on page 25

01:53:26 i'm sorry to keep interrupting you i think it was quite important we get one thing clear we were

01:53:30 looking a little earlier at the email from sasha cruz asking you whether the certificate could be

01:53:37 issued and i think you said but i just want to confirm this that you did see the certificate

01:53:44 in the form in which it was subsequently issued before it was issued is that right

01:53:49 it was the evidence suggests it was sent to me via email and therefore

01:54:02 i must assume that i looked at it even though i have no recollection of such

01:54:10 it's possible there's no record of me responding to to to sasha cruz because it was

01:54:18 a verbal you know yes if they've got the certificates in place send it off

01:54:25 words to that effect there would there would be no formality to it i had assumed that if the

01:54:31 certificate had been sent to you for your response to the question then you would or at least should

01:54:41 have looked through it before you know the certificate was not sent to me

01:54:47 specifically with that question the certificate was circulated to the members of the working group

01:54:55 and it was for the members of the working group to bring it to my attention if they were concerned

01:55:04 about it that i understand it was just that that's the only way that that certificate was sent to me

01:55:13 right but then you receive right then you receive the request from sasha cruz could she issue could

01:55:19 the certificate be issued and i was under the impression that you had in had the certificate

01:55:27 in your possession or a copy of it or that you were sent a copy of it before you answered the question

01:55:35 i can neither deny or confirm that i've no recollection of i don't recall other than as i've

01:55:45 described receiving the the email to the members of the group i don't recall being sent the email

01:55:57 would would assume that i'd seen it because of the previous correspondence all right well i mean the

01:56:03 point really i was in want to invite you to comment on is is this it might be said that you

01:56:12 should have read through the certificate before you approved its issue and if you'd done that

01:56:19 properly you would have spotted the error which you accept it contained is there anything you'd

01:56:25 like to say about that um not really because i don't recall reviewing the certificate i don't recall

01:56:38 being asked

01:56:42 the email suggests that um it should have happened the way you describe it

01:56:49 i don't recall that it happened that way i can't say one way or the other whether i did it or not

01:56:59 the information on that certificate i've agreed is today i don't see it as being correct

01:57:09 um how i viewed it at that time i can't in all honesty recall um it was obviously not read

01:57:19 to the in the detail and the understanding that i've got today and do you think it should have been

01:57:28 hindsight is a wonderful thing and i would say today yes of course um that's not the environment

01:57:36 that we were working in at that time all right well that's very helpful thank you very much

01:57:42 yes yes can you explain why that wasn't the environment you were working in at the time

01:57:48 why when you're sent an email from miss cruise flagging up a particular issue about this

01:57:53 certificate should it be a system approval or not so she wasn't just sending it you to approve she

01:57:58 was saying there's been an issue about this certificate can you confirm why was the environment

01:58:03 in which you were working not one in which you would then thoroughly check that certificate for

01:58:08 its technical accuracy because i was relying on the the work of others i think um is the best way

01:58:19 i can describe it um there was a i don't want to you there was a trust there was an understanding

01:58:33 there was a belief that others were capable of making those decisions

01:58:48 and i was focused on other things right yes in your statement you've said at paragraph 75

01:58:57 on page 25 i was not involved in the checking process and would not have reviewed the certificate

01:59:05 it's very definite evidence you give in your statement now you've seen the documents

01:59:09 can you be so sure

01:59:17 that i would not have reviewed the accuracy of the content of those documents as i've said

01:59:31 they indicated certification by others that were that were being met and that would have been an

01:59:41 overview that i would have accepted yes i see you were the only individual approached to approve

01:59:50 this certificate so far as the documents tell us um does that suggest that it was only you that

01:59:58 could have reviewed it was there anybody else at the time that would have been approving these

02:00:04 certificates i think approving the certificate is is a a strong word and a strong assumption

02:00:15 there was a an agreement that the peer review group would um raise issues

02:00:27 yes and they did without and they doubt the agreement without the agreement of the peer

02:00:32 review group i would not have expected and it certainly wasn't incumbent upon me to overrule the

02:00:42 the peer review group um who am i to say that i know better than they do

02:00:50 and so that i would not agree with right what was the purpose in you seeing it then

02:01:00 if you were just trusting others to get it right and there was that trust and that belief that that

02:01:04 would be right why send the certificate to you at all why not well what was because of uh it was

02:01:14 the part of the staff involvement it was also circulated to the chief executive why send it

02:01:21 to him but but what what did you think you were doing i was i was being included as a matter of

02:01:29 courtesy in information that was being discussed within the the lobc ranks i see as a matter of

02:01:41 courtesy let's move on then just a few more detailed questions about the the objective of

02:01:49 this type approval system let's just go back to the manual this is hbc 6049 and i want to look

02:01:56 at page nine paragraph 1.2 sets out some of the objectives of the type approval certificate

02:02:07 here we have it at the bottom of the page and it tells us this the object of the type approval

02:02:11 is to issue a singular initial building regulation approval certificate in respect of standard

02:02:16 construction matter such certification will deem the matter to comply with the building

02:02:22 regulations and will apply to all following user uses of the particular form of construction

02:02:28 falling within the scope and terms of the certification now is that how you understood

02:02:33 it at the time that was in the manual that's very strong wording i didn't write it i was not party

02:02:43 to the manual it's likely that it would have come from the need to promote something

02:02:56 to draw attention to local authority building control to attract competitors to use it so

02:03:04 um the in that sense uh you know the things are viewed differently today

02:03:12 are you saying that you never saw the the no i can't say i never saw it i can't say that i

02:03:19 viewed it in the way that i do today right did you ever raise any concerns about the language

02:03:28 that was being used you've said it's quite strong language there about it's going to be

02:03:32 deemed to comply did you ever raise any concerns about that no as head of technical no

02:03:40 and why not can you help it was a it was a sales document for for want of a better

02:03:47 description and i didn't see it as a um a technical document at the time my understanding is this

02:03:55 this manual was primarily to help people like mr jones when they were putting these assessments

02:04:01 together isn't that right and it was put together by the uh the peer review group it wasn't put

02:04:07 together by me no but you would have had the authority to question it wouldn't you at the time

02:04:13 if you'd wanted to i was a member of staff authority is perhaps a strong word i could have

02:04:20 commented on it but it would be for the um the review group and the board of directors to decide

02:04:29 what what went and what didn't not me yes and we see below that our purpose in developing and

02:04:36 offering a type approval service are two and i just want to look at the first bullet eliminate

02:04:41 repetitive building regulation checking operations and then the third bullet as you've explained

02:04:47 already ensure consistency across the building control process again were you aware of that

02:04:53 wording eliminate repetitive building regulation checking operations

02:05:02 i didn't i obviously didn't see it as so objectionable that it was necessary to

02:05:08 raise it at the time um it's a way of marketing a service that basically local authorities

02:05:20 didn't have to to sell um and um to to draw attention to them so

02:05:29 i would not have read it in a in an aggressive format okay let's just look at another passage

02:05:36 bottom of page 13 there's a section called using the certificate in this manual

02:05:44 right the heading appears right at the bottom of that page using the certificate and if we go

02:05:48 over the page the manual says this first bullet the certificate holder or their agents should when

02:05:58 submitting relevant building regulation applications enclose a copy of the certificate with the

02:06:02 deposited documents and then the second bullet the local authority in receipt of such applications

02:06:09 shall record that fact in their records and not re-examine any of the matter covered by the

02:06:14 certificate in relation to that application do you see that yes again that's pretty

02:06:22 it's pretty strong stuff isn't it it's it's suggesting that these certificates have a

02:06:28 major impact in terms of what happens on a project yes yes and again were you aware of that at the

02:06:36 time no you weren't aware that that language had been used no were you aware that that was

02:06:43 in practice what happened with these certificates on sites no i didn't know um in great detail

02:06:55 how local authorities or manufacturers used these certificates i didn't have that

02:07:02 involvement with them um and i have no recollection of uh of

02:07:09 reading that or being aware of it or thinking it objectionable at the time right but i mean

02:07:18 it does suggest doesn't it that there's a real imperative in these certificates being

02:07:23 technically accurate if that's going to be the effect on site doesn't it yes

02:07:29 and and just for completeness let's go to page 10 paragraph 2.1 of the manual

02:07:34 this is outline of type approval process and seventh bullet down under using the certificate

02:07:42 which is there in capital letters it says customer submits certificate information in support of

02:07:48 subsequent building regulation applications all local authorities accept certificate within

02:07:54 its terms and limits without further checking were you aware of that language

02:07:59 no i can't recall reading the doc it wasn't a document i needed to know because it wasn't a

02:08:08 process that i was involved with on a day-to-day basis and i was not a product provided by the

02:08:27 product provider that wanted it and i wasn't a local authority that was trying to implement it

02:08:38 and and therefore um i think it extremely unlikely that i would have read it in a critical manner

02:08:48 no i see you say in your statement for the transcript this is at paragraph 28

02:08:57 on page seven you say there could never be a guarantee that an individual local authority

02:09:02 building control officer would accept a system approval or have specific regard to it but that

02:09:09 was that was my understanding not what that document said which would tend to suggest

02:09:16 i wasn't aware of the wording of that document right so you accept that what you've said in

02:09:21 your statement is flatly contradicted by the instruction what i said in my statement is what

02:09:27 i believe right but you accept it's flatly contradicted by what we see in this type

02:09:32 approval manual it does not agree with what is written there

02:09:36 now i just want to ask you a few questions about mr jones's evidence to the inquiry

02:09:48 about his understanding of the purpose of the labc certificate and he told us i'm going to

02:09:54 paraphrase but he basically told us that he had a specific role for in the team for marketing

02:10:01 activity at the time and he viewed the type approval system very much as a marketing tool

02:10:09 to raise the profile of the labc brand was that how you understood it at the time

02:10:16 yes yeah

02:10:21 because regions were encouraged to have a person like mr jones to promote the use of local

02:10:28 authority building control and he said that in terms of marketing the system approval served a

02:10:36 benefit to everyone involved he said that kingspan would benefit through their association with the

02:10:42 labc brand the labc would have its profile raised through being promoted as part of kingspan's

02:10:48 marketing literature and in turn herifordshire would benefit through its association with the

02:10:53 labc do you agree with that i'm not a salesperson so i'm not in a position to agree or disagree with

02:11:01 it no

02:11:08 and he said that he was essentially picked because of his role in the team in marketing rather for

02:11:15 rather than for any technical knowledge or expertise on his part is that consistent with

02:11:21 your understanding of why mr jones was chosen to put together that first k-15 certificate

02:11:29 no i don't have an understanding of why he was chosen so you can't help i was not involved in

02:11:36 his his choice so i can't comment mr jones said that he was reticent about undertaking the

02:11:43 assessment because he didn't have the requisite knowledge but his evidence was that he was advised

02:11:48 by somebody at the labc not to worry too much and he was effectively instructed to do a cut and paste

02:11:55 job of the bba certificate now can you help us as to whether that's correct or not well it certainly

02:12:03 wasn't me but are you aware of whether any of your colleagues i have no idea um i i can't um

02:12:12 um i can make an assumption and we're not here to make assumptions or guesses as to as to why that

02:12:21 occurred so i have no comment to make right mr jones said he was led to believe in a telephone

02:12:27 call he had with somebody at the labc which he thought might have been mr harrison phil harrison

02:12:32 although he couldn't remember for sure that there would be a process of checking any assessment that

02:12:38 he made by the labc and this was part of the reason why he agreed to take on the assessment

02:12:44 process again can you help us as to whether any of your colleagues ever reassured mr jones

02:12:51 that there would be a process of checking any technical assessments he made not i'm not aware

02:12:58 of any discussions of that nature

02:13:06 if we just look at what the type approval service manual said if we can go back to the manual hbc

02:13:12 6049 at page 16 and i want to look at paragraph 3.2 on page 16 there's a whole section here called

02:13:24 assessment checking level of service

02:13:30 and i want to read the third paragraph down it says a required quality feature of the type

02:13:34 approval assessment process is that a second check is incorporated it helps to secure comprehensive

02:13:40 assessment and can be utilized to bring any required specialist skills into play a number

02:13:46 of optional routes can be followed for this purpose which should be applied to best suit the case

02:13:51 these could include and then if you go down sending the project to a second local authority

02:13:59 for an independent check forming a group working panel drawn from a number of authorities

02:14:04 or other pertinent sources do we take it from the emails we've seen that it was that second

02:14:09 bullet that was in play here form a group working panel no from the emails the the

02:14:19 the working group panel that you're inferring there is the

02:14:28 the labc committee members committee of members which is not the same thing that that would be

02:14:35 forming a specific working panel of people from a given region or with a given knowledge not the

02:14:43 general committee membership of the of the the review group so can you help us as to what

02:14:52 checking process according to this manual was actually followed in relation to this first k15

02:14:58 certificate no because i wasn't party to it i see can you explain how whatever checking process was

02:15:10 followed they failed to identify the serious errors in the k15 certificate

02:15:20 i can't explain it and the serious errors that you refer to

02:15:29 um

02:15:34 need to be more specific what which particular or if there's a number what serious errors we

02:15:44 we've accepted that there were errors and previously there's been explanations as to why so i'm not

02:15:54 quite sure what what your what your question is aiming for i'm trying to understand how the labc

02:15:59 managed to issue a certificate that said that k15 could be considered a material of limited

02:16:05 combustibility as we've gone through previously i i can't and i can't enlarge on what i've said

02:16:16 previously so in that sense i can't enlighten you and i can't answer the question okay let's move

02:16:24 forward in time then because what we see in the documents is that a number of concerns were raised

02:16:30 by third parties following the labc issuing this system type approval certificate for k15

02:16:37 and we can see from the documents that in particular rock wall raised a number of concerns

02:16:43 about the claims being made and i want to look you've dealt with this briefly in your witness

02:16:50 statement where you say you've got no recollection of responding to this but let's look look at the

02:16:56 letters that you received and your response so let's start with mr kody's letter at labc 40924

02:17:13 so this is addressed to you

02:17:19 and we believe this letter is dated september 2009 and he says in the first and second paragraphs he

02:17:28 says it's about kingspan k15 and first to make the grade with labc newsletter we have been made

02:17:36 aware of the attached article newsletter currently appearing on the website of the insulation

02:17:40 manufacturer kingspan entitled first to make the grade with labc which relates to its k15 phenolic

02:17:47 plastic foam insulation product this article asserts that labc has stated that k15 can be

02:17:54 considered a material of limited combustibility and is suitable in all situations shown on diagram

02:18:01 40 of approved document b volume 2 including those parts of a building more than 18 meters above ground

02:18:07 this claim is of serious concern and then below that what mr kody does we'll see at the end that

02:18:16 that's the author of the letter is he goes on to explain under the building regulations and in

02:18:21 particular the guidance in approved document b how a material of limited combustibility is classified

02:18:28 according to table a7 and he gives information about the tests and the classification standards

02:18:35 used to pursue this

02:18:39 and he says in the the fourth paragraph under that heading materials of limited combustibility

02:18:45 we therefore ask you to please confirm whether labc has issued a statement that k15 can be

02:18:50 considered a material of limited combustibility if labc has issued such a statement we ask you

02:18:55 to please provide a copy of it together with an explanation of the basis on which it was issued

02:19:00 furthermore we ask you to please confirm whether the kingspan brochure provides a fair and accurate

02:19:04 representation of labc's position and then they go on to discuss diagram 40 of approved document b

02:19:12 and note that kingspan asserts that the labc has stated that k15 is suitable for all situations

02:19:18 shown in diagram 40 and and the letter goes on if we go over the page

02:19:28 it's acknowledged at the top of that page that there are alternative ways

02:19:32 to comply with the requirements of the building regulations for example performance criteria in br

02:19:36 135 successful testing bs 8414 but then it says however these tests are intended to evaluate the

02:19:44 performance of the entire proprietary systems and not just the insulation material within the cavity

02:19:49 behind a cladding system in isolation from other components and then in the next paragraph they say

02:19:57 bearing in mind that clause 12.5 of section 4 of adb lays out the principles for external wall

02:20:03 construction and states that the use of combustible materials in the cladding system and extensive

02:20:07 cavities may present such a risk medium for fire spread in tall buildings it is of concern that

02:20:13 labc is cited by kingspan as offering an opinion which could result in a combustible insulation

02:20:19 material being used in an application where a potential risk has been clearly identified

02:20:25 we therefore ask you to please confirm whether you've issued that statement

02:20:30 and then they say in the final paragraph we're currently in a position to comment only on kingspan's

02:20:35 representation of the labc's position and we'd like a response to properly assess what further actions

02:20:43 yours sincerely mr lw cody now it's right isn't it that you didn't respond to that letter that

02:20:52 first letter apparently so yes when you say apparently so do you know i i don't

02:21:01 didn't recall it to be perfectly honest i'm i'm relying on the the information that's

02:21:07 been provided to promote my recollection of it just going down the page i just want to see right

02:21:14 at the bottom i think it's cc this letter to other bodies can you see that there cc to paul everall

02:21:21 the chief executive of labc and mr brian martin principal construction professional at clg now do

02:21:28 you have any memory of receiving this september 2009 letter from mr cody i do now

02:21:38 only in the way it's presented here

02:21:44 sorry i don't quite follow do you actually have a memory at the time of receiving this letter

02:21:51 i have a vague recollection that we had a uh a letter of this nature i couldn't have told you

02:21:59 what it was until it's presented here yeah did you agree with mr cody's concerns as set out

02:22:07 very clearly in this letter uh from recollection i didn't consider them this was a letter

02:22:20 letter of or my recollection is that this was considered a complaint from a competitor

02:22:29 and labc shouldn't act as referee between competitors i put my trust in those that have

02:22:39 dealt with the matter and the certifications that were in place by the likes of bba

02:22:46 rather than believe an argument put forward by a competitor i see did you actually read the letter

02:22:55 did you read that is my you asked for my recollection that is my recollection it might

02:23:02 be one thing to dismiss complaints by a competitor where they're minor or you know nitpicking but

02:23:11 but this letter is raising pretty serious safety concerns about the use of k-15 isn't it

02:23:19 wasn't taken any further by anybody can you help us as to why not given the terms of the letter

02:23:27 no did you carry out any checks on the basis of this letter to look at the certificate

02:23:36 to look at what was in approved document b to check whether the certificate that had been

02:23:41 issued by the labc was technically accurate did you undertake any such this was a complaint from

02:23:48 a competitor so the answer is no so you simply dismissed it because it was from

02:23:55 king span's competitor and you didn't engage at all with the substance of it no

02:24:06 did you ever discuss rock wall's concerns with anybody else within labc we can see it's copied

02:24:13 to mr paul everall the chief executive did you ever discuss the concerns raised in this letter

02:24:18 with anybody else

02:24:23 i have a recollection that i may well have discussed it but i couldn't tell you the content of that

02:24:33 discussion because i don't have no recollection of it so what recollection do you have that you may

02:24:38 well have discussed it can you recall who it was it may yeah it would have been brought to the

02:24:42 attention of uh of the chief exec it may well have been brought to the attention of the board

02:24:49 of directors but i've got no evidence i've got no recollection i can't i can't make that statement

02:24:56 right and did you know who mr brian martin was when you received this

02:25:01 letter he's there cc'd at the bottom yes how well did you know him at this point

02:25:07 reasonably well i i knew i i probably met him on the on the working groups

02:25:16 were you concerned that mr martin was copied in here as the principal construction professional

02:25:21 at the clg didn't that heighten the importance of this letter um quite a bit but i think

02:25:30 quite the opposite i think if there had been um an issue that mr martin thought fit to raise

02:25:38 i would have hoped that he would have raised it with me so the fact that it was copied

02:25:44 and not responded to diminished the the strength of the letter i see so the fact that you didn't

02:25:53 subsequently hear from mr martin about this what gave you some kind of reassurance that there was

02:25:59 no problem no i can't say that was the case at all but the fact is there was no response

02:26:08 and the fact is it was treated as a complaint from a competitor

02:26:15 just help us when was the first time you became aware that there was erroneous information in the

02:26:21 k-15 type approval certificate when when the discussion when when the discussion started to

02:26:30 evolve around the the change in the bba certificate right so later 2013 2014 are you saying that sounds

02:26:40 about right okay now mr cody wrote a further letter to you on behalf of rockwall let's look

02:26:47 at that labc four zeros 853

02:26:57 and we believe the letter is not dated but we believe that this letter was written in october

02:27:02 2009 so about a month after the first letter and it states this and again headed kingspan k-15

02:27:11 phenolic insulation etc we wrote to you in september regarding an article first to make

02:27:17 the grade with labc this appears on the website of kingspan insulation in which they claim the

02:27:22 labc have stated that their k-15 product can be considered a material of limited combustibility

02:27:29 as i'm sure you are aware the appropriate fire classification claims on construction products

02:27:34 is extremely important with respect to both life safety and property protection

02:27:40 therefore we wish to clarify the basis of the statement appearing on the kingspan website

02:27:45 before considering any future activities whilst we understand that you may need time to consider

02:27:50 your response we would appreciate your acknowledged receipt of the original letter

02:27:54 dated 25th of september and provide an indication of when you are likely to respond yours sincerely

02:28:01 mr cody now um again i think it's right isn't it that um you didn't respond to this letter

02:28:12 in the days after it was received am i i have a recollection that there is on record a response

02:28:22 to this letter and it follows what i've already told you there is much later but there isn't at

02:28:28 this point there is a response in february 2010 but we're in october 2009 at this point can you

02:28:35 explain why you didn't respond promptly to this letter which is raising questions about life

02:28:42 safety and property protection in relation to claims that have been made about labc statements

02:28:48 no

02:28:53 do you remember making a conscious decision not to respond

02:28:59 no i don't i don't recollect how it was dealt with at all i'm afraid right we can see that on

02:29:07 the 1st of february 2010 mr cody writes an email to someone called stacy roper if we go to labc

02:29:15 two zeros 10318 and look at the bottom of page three

02:29:26 right at the bottom there we can see mr cody to miss roper first of february 2010 says hi labc do

02:29:35 you have a service charter and a procedure which will address concerns regarding the service provided

02:29:39 by the labc if so can you please forward a copy to me now we know from other emails that miss roper

02:29:47 was a support services and communications assistant at the labc does that sound right

02:29:55 i'm sorry i don't recollect stacy roper

02:30:00 okay and then we can see at the top of page three miss slater slater responds that same day 1st of

02:30:07 february saying good morning larry labc does not provide a building control service and therefore

02:30:12 we have no service charter relating to this the building control service is provided by individual

02:30:17 local authorities who will have their own service level agreements please note that labc is not a

02:30:22 governing body for local authorities any concerns or issues with individual authorities will need

02:30:26 to be raised with them i hope this helps now and then if we follow this chain through at the bottom

02:30:35 of page two mr cody responds again on the same day first of february he says this my issue is

02:30:42 not with the local authority but with a lack of response from labc regarding two letters addressed

02:30:47 to your mr barry turner and sent in september and october 2009 the latter was merely to ask for

02:30:52 confirmation that the first letter had been received and to ask for an indication on when

02:30:56 we could expect a response i would very much prefer not to invoke any sort of formal complaint

02:31:01 as i expect there's a very good explanation as to why these letters have not been answered

02:31:05 but on the other hand i would be very grateful to receive a considered response at the earliest

02:31:09 opportunity do you see that yes now just pausing there there was a complaints procedure in place

02:31:17 at the time were you aware of that not really no if we look at the labc manual again hbc six zeros

02:31:29 49 and this time at page 30

02:31:41 at paragraph 8.2 there we can see towards the top of the page it says local authorities and

02:31:48 labc should have complaints procedures according with building control performance standard 12 the

02:31:53 labc type approval service complaint procedure is as follows and then there's a staged approach

02:32:01 all complaints verbal written electronic that don't fall under the adjudication scheme will be

02:32:07 indexed in a complaints register an acknowledgement then sent setting out the procedure

02:32:13 complaint will be investigated item three by a person independent of the matter etc

02:32:18 now can you help us as to why mr cody's letters weren't dealt with in accordance with this

02:32:25 complaints procedure his letters asking for them weren't addressed to me so no i can't help you

02:32:33 ought mr cody's letters have been referred under this formal complaints procedure it would seem

02:32:40 he asked for a complaints procedure if there was one available

02:32:47 then he should his attention should have been drawn to it but

02:32:52 that correspondence was not addressed to me so i can't answer the questions as to why

02:32:57 that didn't happen well the later correspondence wasn't addressed to you but the earlier letters

02:33:02 were the earlier letters were but when he was asking about a complaints procedure they were

02:33:06 not addressed to me and you were never made aware of and i was not made aware of it to my knowledge

02:33:11 or to my recollection it's right isn't it that had the complaint been dealt with in the appropriate

02:33:17 way and an investigation carried out by a person independent of the matter the labc might have been

02:33:23 able to identify at that stage that there was inaccurate information in the labc k-15 certificate

02:33:29 that's right and it could have been amended that is correct yeah now the following day

02:33:36 we can see if we go back to labc 0010318

02:33:44 you say you weren't made aware that mr cody was asking about the complaints procedure

02:33:49 in fact what we see if we go to the top of page one in this string

02:33:59 we can see louis slater says to you on the 1st of february 2010 hi barry please see the attached

02:34:07 letter from larry at rockwall which he sent in september of last year please could you advise

02:34:12 if a response was ever sent to this do you see that yes do you remember miss slater drawing this

02:34:18 to your attention again that's the letter that we've already discussed yeah that refers to the

02:34:25 letter that we've already discussed so you weren't aware of the string below that where

02:34:31 he was asking about the complaints procedure no no okay we can also see that on the 8th of february

02:34:39 2010 someone called john garbett of kingspan he was the head of marketing at kingspan

02:34:46 wrote an email to you let's look at that labc 0019617 it's the second email down

02:35:03 and we can see that john buck garbett says to you

02:35:06 8th of february barry your email to richard bromwich was forwarded to me to deal with see

02:35:12 attached the system approval paperwork for the product and the original press release that was

02:35:16 posted on our website this press release is no longer on the website as it has been superseded

02:35:22 by newer items clearly we were quoting the content of the system approval and we consider that we

02:35:29 we did not in any way overstate the case should you like to discuss please let me know would it

02:35:36 be okay for us to let our contact in here for june know of the concerns raised by rockwall

02:35:41 so that he isn't caught cold so you appear to be discussing this complaint with the head of

02:35:48 marketing at kingspan in february 2010 that's right isn't it the letter is from him or the

02:35:55 email is from him that's correct and on the same day you respond if we go to the top email

02:36:03 in this chain 9th of february 2010 john i need to look at this more closely but for the moment i

02:36:09 have no problem with you advising colleagues of the matter although i would prefer if you did not

02:36:14 circulate the original rockwall letter i'm trying to be open and fair with everybody but i don't

02:36:20 appreciate such confrontational approaches so you said i need to look at this more closely did you

02:36:29 in fact look at it more closely it would appear not no sorry can i just ask you how well did you

02:36:37 know mr garbert i see you're on first name terms i knew him very well because of his again expertise

02:36:44 in thermal calculation and thermal performance working on the the the dclg working groups and

02:36:54 i think he was also involved with the zero carbon hub that i was also it was all thermal performance

02:36:59 related which is why i knew them good thank you very much i'm sorry i cut it no no it's fine

02:37:05 can you explain why you were discussing this with the head of marketing at kingspan before you've

02:37:11 even investigated the substance of the complaint that's been raised i think the first

02:37:21 connection or the first the first correspondence came from them not from me and it came from them

02:37:26 because he knew me through the working group not the other way around you say here that you'd prefer

02:37:33 in the second line you say i prefer if you did not circulate the original rockwell letter why

02:37:39 were you wanting to keep the rockwell letter to a small circulation group at this time i

02:37:48 viewed it as a

02:37:52 a complaint from rockwell as i said from between one competitor and another and so

02:37:59 um i was asking for a for a view on it because i

02:38:06 knew um or knew of them and because of the uh the previous contacts with labc not necessarily my own

02:38:16 contacts in in relation to the to the type approval yes so it was one of courtesy

02:38:23 yes but what we're seeking to understand is why would you seek kingspan's view on this complaint

02:38:28 before you've even ascertained what the nature of the complaint was and whether there's any

02:38:33 substance to it in independently of kingspan perhaps i was asked because they had provided

02:38:41 certification that supported their product but it was your certificate that certificate was based on

02:38:53 um

02:38:55 certificates issued by testing laboratories and testing facilities and because they had

02:39:06 accredited test certificates for their products um i chose to believe that those accredited test

02:39:16 certificates were correct and if that was the case then why was there a complaint being made

02:39:26 against them well did it occur to you that there might have been a simple error in transposing the

02:39:32 information in the accreditation certificates into your certificate

02:39:38 um

02:39:41 no to be perfectly honest um it's not something that was it was not a um

02:39:53 i don't recall and obviously because there's no evidence to suggest i did

02:40:00 carry out that then then it would appear not i have no recollection of it to be honest

02:40:05 thank you okay um on the 23rd of february you did uh 2010 you responded to mr cody's letter

02:40:14 if we look at that labc 0019618

02:40:35 here it is it's from you to mr cody copying in sasha cruz philip hammond and someone called

02:40:42 elwyn jones and you say this i refer to your letter requesting explanation of the labc system

02:40:48 approval issued for the above product and statements apparently made on the kingspan website

02:40:54 with particular reference to the k-15 product at the time of consideration the local authority

02:40:59 that carried out the assessment for compliance with the building regulations were satisfied that

02:41:04 it met the relevant criteria on that basis they felt able to recommend to other members that under

02:41:10 the circumstances described the material met the requirements of building regulations you go on

02:41:16 labc is a private company run by members for the benefit of those members and it is not for us to

02:41:21 explain to third parties our reasons or justification for the business of labc our intention is to be

02:41:28 fair and reasonable to all parts of the construction industry and work with industry for the benefit of

02:41:32 all concerned we would much prefer to work with your company and promote the benefits and

02:41:37 specialities that you have to offer rather than respond to your challenges of competitor products

02:41:43 this is now your second challenge on this rival manufacturer relating to compliance with part b

02:41:48 of the building regulations if you have issues with claims made by a competitor i must ask that

02:41:53 you deal direct with the company making those claims if labc have any concerns over statements

02:41:58 made or reference about an labc service it is for us to take up that matter with the party direct

02:42:04 i do not consider that it is a matter for discussion with a competitor if you would like to meet to

02:42:10 discuss how we may work together to promote good practice and solutions and make labc members aware

02:42:15 of the benefits of your company products and services i'd be very happy to do so i do not

02:42:19 however feel there's anything to be gained by your challenges of information we provide

02:42:25 do you see that there yes now from your response and particularly that second paragraph it appears

02:42:31 that you're not only agreeing with mr jones's assessment of k-15 but you are in fact defending

02:42:38 the technically incorrect claim made on that certificate is that right i put my trust in

02:42:45 others that they had done it correctly and as an organization representing local authorities

02:42:53 of course we were trying to defend them and was it purely that that by the time you wrote this

02:43:04 letter you still hadn't engaged with the substance of the complaint that was being raised yes

02:43:13 had you not appreciated by this time you've had a long time to think about it that the certificate

02:43:19 was technically inaccurate and misleading in a pretty major way by describing it as a limited

02:43:25 combustibility or can be considered of limited combustibility considering the

02:43:36 lack of involvement with the whole process of this certificate i have been drawn into something

02:43:45 um that's up to the point of receiving these letters i'd had no real involvement with

02:43:53 and so that is the the view that i took at that time

02:44:01 and others involved that had been in you know were not raising concerns and others involved

02:44:10 had got more knowledge of what was going on than i had

02:44:16 i see so you're saying because you weren't really involved with the

02:44:20 the certificate process that's what you're saying now you didn't really have any involvement with

02:44:26 this and so you just defended the certificate i put my trust in the people that have dealt with it

02:44:34 you suggest in this letter that rockwall should deal directly with king span about the labc

02:44:39 certificate how was that appropriate or practical it was your certificate not king spans

02:44:46 uh maybe the wording is not particularly um correct but the the principle was that

02:44:56 they should make a a complaint direct to the the person making the statement or to if if there was

02:45:04 an issue with a product and as i've said before this was seen as an argument between two competitors

02:45:15 with alternative products if they thought that the product was not right and again i was defending

02:45:24 the process that had been carried out in checking the certification put forward by king span

02:45:32 um then they the the approach that they should make was not through labc yes you say there was

02:45:43 a principle that they should make a complaint direct to the person making this statement but

02:45:47 rockwall are telling you that kings ban are quoting from your certificate so why weren't

02:45:53 you the appropriate people to be dealing with that complaint i can't answer that question and

02:45:58 i didn't see it that way at the time right

02:46:07 if we look at a document labc 0019620

02:46:15 second email down in this string

02:46:21 we can see that uh your colleague alwyn jones what role did alwyn jones have at the time

02:46:29 um he was a

02:46:36 technical

02:46:40 assistant helper

02:46:45 brought brought on board i as much as i recall to to

02:46:50 to put labc and have a greater involvement in the type approval process

02:47:01 and we can see he says if i do say so myself very good mr turner and then you say thanks al

02:47:08 not so sure mr kody will agree so you must have anticipated that rockwall were not going to be

02:47:14 satisfied with your response yes yeah did you appreciate the public safety ramifications of

02:47:20 being so dismissive to rockwall's concerns if i had appreciated that i wouldn't have dealt with

02:47:27 it in the way that i did but do you accept now that they were absolutely clear on the base of

02:47:36 those letters raised and viewed with today's knowledge um it could have been dealt with

02:47:44 in a more appropriate manner it was viewed as a complaint between competitors at the time

02:47:51 we see today that wasn't the way to view it but that's the way it was dealt with at the time

02:47:59 now just to complete this mr kody then responds if we go labc 0019632

02:48:06 and look at page three of the string

02:48:14 here we can see on the fourth of march 2010 he says thank you for the response to my letter and

02:48:21 clarification of labc's position as you suggest it's preferable to raise such issues directly

02:48:26 the company concerned as a first step in this process we wish to seek confirmation that labc's

02:48:31 opinion was as publicized by king span having now received this confirmation from you we can consider

02:48:36 our actions towards king span direct or through other channels the fact that we have sought such

02:48:41 fact that we have sought such clarification from you is an acknowledgement by manufacturers

02:48:45 of construction products as to the influence that the labc has in such matters and it goes on we

02:48:52 hope that we will be able to continue to engage with labc on important matters affecting the

02:48:56 construction industry and then he says we'd welcome your suggestion of a meeting to discuss

02:49:03 ways of working together and we can see you respond to this if we go on page two one email

02:49:10 up in this string you say thank you for your response i must for the record state that my

02:49:17 earlier message neither accepted nor denied the statements publicized by king span merely

02:49:22 indicated that we consider it's not a matter to discuss in this context with a third party

02:49:27 now pausing there why did you say that i can't recall um

02:49:33 um clarification um i don't know i mean those statements were matters of fact weren't they

02:49:45 they weren't there to be neither confirmed nor denied the statements that had been made about

02:49:49 k-15's properties i suppose i was trying to protect labc's you know involvement i i really

02:49:57 don't know why why that wording was used in that particular context at that particular time

02:50:03 right and you go on you say i would however like to draw a line under this exchange and move on to

02:50:08 more constructive discussion cooperation with us did you ever have any further discussions with

02:50:13 mr kody or rockwall about uh this complaint not that i'm aware of now in addition to mr kody's

02:50:22 complaint we know that the labc received an email from someone called jim mansfield of the

02:50:27 jim mansfield consultancy in april 2011 expressing concern about king span making misleading claims

02:50:34 so just to help you this is now over a year later let's look at this email labc 0019671

02:50:43 and it's the bottom of the email chain on page two email at 1047

02:50:55 mr mansfield says to miss sloper subject misleading claims by king span dears says i'm an accredited

02:51:04 energy assessor and chartered building services engineer i'm very concerned that king span who

02:51:09 is an engineering engineer i'm very concerned that king span who manufacture insulation products

02:51:13 are making misleading claims this will lead to many buildings which will not comply with

02:51:17 the requirements of the 2010 version of part l i believe that sellotex are similarly guilty

02:51:23 is this something you can resolve do you need me to address to provide further details now to be

02:51:28 clear he seems to be raising concerns about part l in terms of thermal efficiency there we see in

02:51:35 the same chain miss sloper forwards this email to you and mr bassin on the same day page two

02:51:43 she says uh hi barry and doug please see the email below mr bassin then responds he says

02:51:50 this is strange not sure but i had a real wise guy at the eco build come up to me and start

02:51:55 challenging me on all sorts of stuff turned out he was of the same credentials as this person

02:51:59 is it possible it could be one in the same person barry do you want to lead on this as

02:52:05 if it's part l i'm not happy to start the process sorry if not i'm happy to start the process off

02:52:10 as we will have to respond in some sort of way and then further up you respond you say i'll

02:52:18 answer it just in the process of not our problem and he will be told so now i appreciate this is

02:52:27 part l but it's king span again and it's misleading claims being made by king span

02:52:32 and why did you not take those concerns more seriously at the time and investigate them the

02:52:41 whole industry focus at that time was on thermal performance

02:52:51 and a very scientific process as to how you determine the thermal performance of materials

02:52:58 of materials way beyond the the capabilities of of surveyors so it was a calculation process

02:53:07 as far as compliance with regulations are concerned so it was not

02:53:15 should we say there was no connection made as far as i recall between this issue

02:53:22 and the ones that we've previously been discussing

02:53:25 and let's look at the chain and how i don't know whether you've got a copy of the response i've

02:53:32 absolutely no idea what sort of what response i made yeah i'm coming to it and so miss slo if

02:53:38 we keep going with the chain miss sloper then replies one one email up at 1106 she says not

02:53:46 sure if it's relevant but king span has some system approvals with us and then you say yes i

02:53:52 suspect that is why he's contacted us but if he doesn't give us any information he can't expect

02:53:56 much of a reply three exclamation marks well he won't get one and then we can see your response

02:54:06 at labc 0019673

02:54:10 so here on the 8th of april 2011 you write to mr mansfield and you say dear sir i refer to your

02:54:25 message below that's been passed to me for a response if you have an issue with claims made

02:54:29 by a particular company you should in the first place take up with them direct and follow their

02:54:33 established complaints procedure you may wish to verify claims by their third party accreditation

02:54:39 if there is an appropriate certificate of performance produced by a british or european

02:54:43 accredited testing station without further information i'm unable to comment further

02:54:48 labc is a member organization operating for the benefit of its members we do not govern

02:54:53 authorize or control commercial organizations so that was your response um did you not think to

02:54:59 ask mr mansfield for further particulars about what his concerns were at this time this is the

02:55:06 second time does that letter not invite further for a corporate further correspondence if he

02:55:11 wants me to follow it up you've said there without further information i'm unable to comment further

02:55:18 so are you saying that if he'd got further complaints you expected them to come back after

02:55:23 this yes right i see and did you not make the connection with the complaints that you'd had

02:55:29 from rockwall a year earlier about statements kingspan were making i've already answered that

02:55:33 and said no i didn't i see

02:55:40 mr chairman that's actually quite a good moment i know it's five minutes early to to probably

02:55:45 break because i'm moving to a slightly different but related topic all right and i'd rather take

02:55:50 that in one go it won't be disasters if we have uh five minutes longer for lunch will it i i don't

02:55:56 think so no i think that's fine um well thank you as you've heard mr turner that's a convenient

02:56:03 point in council's line of questioning to have the break that we would be having in a few minutes

02:56:08 for lunch in any event so we'll stop there uh we'll resume at two o'clock please and again i must

02:56:15 ask you not to discuss your evidence or anything to do with it with anyone over the break all right

02:56:20 thank you very much would you go the usher please

02:56:38 thank you very much